County Durham: housing land supply, local plan and appeals

Durham County Council says it can show a 3.92-year supply of housing land, at 1 April 2026, measured against local housing need (standard method, 2,036 homes a year) plus 5% buffer, short of the five years national policy asks for.

The four most recent appeal decisions that dealt with land supply, from 1 April 2026 to 4 August 2026, all found the council could not show five years. Before that, inspectors found it could, most recently on 3 September 2025.

It scored 131% in the 2025 Housing Delivery Test, with no consequence listed.

Its local plan, the County Durham Plan (2020), was adopted on 1 July 2024. A replacement, the County Durham Plan (replacement), is at the scoping consultation.

Updated 2026-11-17 (2 days ago). Every figure links to where it comes from.

Five-year housing land supply

Durham County Council's latest published position is a 3.92-year supply of deliverable housing land for the period 2026/27 to 2030/31, made up of 8,375 homes it expects on deliverable sites. It is measured against local housing need (standard method, 2,036 homes a year) plus 5% buffer.

Other councils in the North East

Each council's own latest figure; base dates differ. All councils are on the land supply map of England.

Source: the council's land supply statement, published 2026-07. Checked 2026-10-02 (7 weeks ago).

What inspectors found at appeal

A council's own land supply figure is often tested at appeal. These are the most recent appeal decisions in County Durham where the inspector dealt with land supply, and what each one found.

  1. Five years not shownNot disputed4 August 2026 - appeal dismissed
    Land To The South Of Playground, Dene View, High Hesleden, County Durham
    “it has confirmed that it can no longer demonstrate a five-year supply of deliverable housing sites. The evidence before me indicates that the current supply stands at approximately 4.4 years.”
    Figures given: council 4.4 years, inspector 4.4 years. Decision 3375932
  2. Five years not shownNot disputed30 June 2026 - appeal dismissed
    LILAC LODGE, EAST TERRACE, RODDYMOOR, COUNTY DURHAM
    “The Council cannot demonstrate a five-year supply of deliverable housing sites, identifying a supply of 4.4 years”
    Figures given: council 4.4 years, inspector 4.4 years. Decision 6006222
  3. Five years not shownNot disputed11 June 2026 - appeal dismissed
    Land South West Of Newholme Estate, Station Town, Wingate, County Durham
    “The Council confirms that it cannot demonstrate a five-year supply of deliverable housing sites, identifying a supply of 4.4 years.”
    Figures given: council 4.4 years. Decision 6006821
  4. Five years not shownNot disputed1 April 2026 - appeal dismissed
    Low Deanery Farm, Adelaide Bank, Shildon, County Durham
    “the Council have indicated that it currently only has a 4.4 year housing land supply and have not disputed that paragraph 11d)ii of the Framework is engaged”
    Figures given: council 4.4 years. Decision 6003412
  5. Five years shownNot disputed3 September 2025 - appeal dismissed
    Land at Hillrise Crescent, Seaton Village
    “The main parties agree a 6.14 year housing supply as of 1 April 2025. On the evidence before me, I am satisfied that the Council can currently demonstrate a 5 year housing land supply”
  6. Five years shownNot disputed28 March 2025 - appeal dismissed
    Land to the south of Greenways Court, Greenways, Delves Lane, CONSETT
    “At this time, the Council has a sufficient supply of housing land, and the policies in the Plan are up-to-date.”
  7. Five years shownNot disputed30 August 2024 - appeal dismissed
    Land east of The Meadows, Seaton, County Durham
    “The Council can currently demonstrate a five-year supply of deliverable housing sites”
  8. Five years not shownNot disputed16 May 2024 - appeal dismissed
    Land North of George Pit Lane, Great Lumley
    “Notwithstanding that the lpa can show a housing land supply in excess of 4 years”

Housing Delivery Test

The Housing Delivery Test compares the homes built in a council's area over three years with the number needed. County Durham scored 131% in the 2025 measurement, published on 17 August 2026. The consequence listed in the government's results is: None.

YearHomes neededHomes delivered
2022 to 20231,2281,561
2023 to 20241,1721,295
2024 to 20251,1291,753

Source: Housing Delivery Test 2025 measurement. Every council's result: Housing Delivery Test results.

Local plan

The development plan is the County Durham Plan (2020) and County Durham Minerals and Waste Policies and Allocations Document (2024), adopted on 1 July 2024.

11 made neighbourhood plans across County Durham, with dozens more parishes at earlier stages.

The County Durham Plan (replacement)

Being prepared under the plan-making system introduced in 2026, which runs each plan through three gateways in about 30 months.

Now at scoping consultation, step 2 of 9.

  1. Notice of intention25 Mar 2026
  2. NowScoping consultation22 June 2026
  3. Gateway 1
  4. Content and evidence consultation
  5. Gateway 2
  6. Plan consultation
  7. Gateway 3
  8. Examination
  9. Adoption
  1. Notice of intention25 Mar 2026
  2. Scoping consultationNow22 June 2026
  3. Gateway 1
  4. Content and evidence consultation
  5. Gateway 2
  6. Plan consultation
  7. Gateway 3
  8. Examination
  9. Adoption

Dates from the council's published timetable, its local development scheme.

Source: the council's local plan pages. Checked 2026-09-20 (2 months ago). Every council: where each local plan has got to.

Planning appeals

Since 2016, inspectors have decided 526 appeals against County Durham's decisions and allowed 130 of them (25%), against 31% across all councils. For major schemes, 16 of 39 were allowed (41%, against 50% across all councils).

YearDecidedAllowedShare allowed
2019419 (22%)
20205115 (29%)
2021445 (11%)
2022478 (17%)
20234310 (23%)
20245312 (23%)
20256615 (23%)
20264417 (39%)

Decided means allowed, dismissed or split, with a decision date; a split decision counts as decided but not allowed. From the Planning Inspectorate's published decisions.

County Durham's own pages

Land supply around County Durham

Barnsley: 2.9 yearsBlackburn with Darwen: 5.7 yearsBlackpool: 2.1 yearsBolton: 3.61 yearsBradford: 3.59 yearsBurnley: 12.3 yearsBury: 4.3 yearsCalderdale: 3.89 yearsChorley: 3.4 yearsCounty Durham: 3.92 yearsCumberland: 2.5 yearsDarlington: 5.4 yearsDoncaster: 6.35 yearsEast Riding of Yorkshire: No current figure publishedFylde: 4.35 yearsGateshead: 2.61 yearsHartlepool: 5 yearsHyndburn: 5.91 yearsKingston upon Hull: 3.16 yearsKirklees: 4.18 yearsLancaster: 2 yearsLeeds: 6.4 yearsMiddlesbrough: 5.2 yearsNewcastle upon Tyne: No current figure publishedNorth East Lincolnshire: 3.6 yearsNorth Lincolnshire: No current figure publishedNorth Tyneside: 2.82 yearsNorth Yorkshire: 2.26 yearsNorthumberland: 7 yearsOldham: 6.7 yearsPendle: 5.32 yearsPreston: 5.48 yearsRedcar and Cleveland: 3.62 yearsRibble Valley: 2.24 yearsRochdale: 5.2 yearsRossendale: 5.3 yearsSefton: 3.34 yearsSouth Ribble: 5.53 yearsSouth Tyneside: Says it cannot show five yearsStockton-on-Tees: 4 yearsSunderland: 4.5 yearsWakefield: 5.5 yearsWest Lancashire: 2.49 yearsWest Lindsey: 7.1 yearsWestmorland and Furness: 3.17 yearsWigan: 5.45 yearsWyre: 8.36 yearsYork: No current figure published
6 years or more5 to 6 years4 to 5 years, or says it cannot show fiveUnder 4 yearsNo current figure published

Each council's own latest figure. The whole country: land supply map of England.

About this page

Planther keeps track of every council's plan, land supply position and appeal record, and rebuilds this page every night from what it holds. Figures are the council's own unless they are marked as an inspector's. If something here is wrong, email hello@planther.co.uk and we will put it right.

See Planther at work in County Durham

Ask Planther about a site and it does the research: the council's position, the appeals that matter, and a first draft, each point with its source. Here it answers a question about County Durham from the figures on this page.

Book a demo

We will show you round Planther, then set you up with a trial so you can try it on your own work. We can usually have you, or your whole firm, up and running the same day.

Bringing a whole firm? We can work to your own contract and data processing agreement, and invoice you directly.