Barnsley Council says it can show a 2.9-year supply of housing land, at 1 April 2024, measured against the Local Plan housing requirement, with backlog added back using the Liverpool method, short of the five years national policy asks for.
The four most recent appeal decisions that dealt with land supply, from 7 February 2025 to 25 February 2026, all found the council could not show five years.
It scored 75% in the 2025 Housing Delivery Test, and the government's results list a 20% buffer as the consequence.
Its local plan, the Barnsley Local Plan, was adopted on 3 January 2019.
Updated 2026-11-17 (2 days ago). Every figure links to where it comes from.