Bradford: housing land supply, local plan and appeals

Bradford Council says it can show a 3.59-year supply of housing land, at 1 April 2025, measured against local housing need (standard method), as the Core Strategy is more than five years old, short of the five years national policy asks for.

The 12 most recent appeal decisions that dealt with land supply, from 27 January 2023 to 10 November 2026, all found the council could not show five years.

It scored 56% in the 2025 Housing Delivery Test, and the government's results list the presumption in favour of sustainable development as the consequence.

Its local plan, the Bradford District Core Strategy DPD (2017), was adopted on 12 December 2017. A replacement, the Bradford District Local Plan 2025-2043, is at Regulation 19.

Updated 2026-11-17 (2 days ago). Every figure links to where it comes from.

Five-year housing land supply

Bradford Council's latest published position is a 3.59-year supply of deliverable housing land for the period 2025 to 2030, made up of 8,033 homes it expects on deliverable sites. It is measured against local housing need (standard method), as the Core Strategy is more than five years old.

This is the latest figure the council has published. Its base date is 1 April 2025, more than 18 months ago.

Other councils in the Yorkshire and the Humber

Each council's own latest figure; base dates differ. All councils are on the land supply map of England.

Source: the council's land supply statement, published 2026-10. Checked 2026-11-12 (7 days ago).

What inspectors found at appeal

A council's own land supply figure is often tested at appeal. These are the most recent appeal decisions in Bradford where the inspector dealt with land supply, and what each one found.

  1. Five years not shownNot disputed10 November 2026 - appeal allowed
    Lockwood Farm, Spen Lane View, Bradford
    “The Council do not dispute that a five-year supply of deliverable housing sites cannot be demonstrated”
    Figures given: appellant 2.08 years. Decision 6010497
  2. Five years not shownNot disputed10 July 2026 - appeal allowed
    Land East of Burley Road, Menston, Bradford
    “The Council's latest published Five-Year Housing Land Supply Statement identifies a significant shortfall, with only 2.08 years' worth of deliverable housing land available.”
    Figures given: council 2.08 years. Decision 6006765
  3. Five years not shownNot disputed10 July 2025 - appeal dismissed
    18 Low Green Terrace, BRADFORD
    “The Council has noted that that they have a Five-Year Housing Land Supply (5YHLS) position of 2.06 years.”
    Figures given: council 2.06 years. Decision 3365435
  4. Five years not shownNot disputed25 April 2025 - appeal dismissed
    2 Mavis Street, BRADFORD
    “The Council is unable to demonstrate the supply of housing sites required by the National Planning Policy Framework (the Framework).”
  5. Five years not shownNot disputed4 March 2025 - appeal dismissed
    1189 Thornton Road, Thornton, BRADFORD
    “The Council cannot currently demonstrate a five-year housing land supply”
  6. Five years not shownNot disputed24 September 2024 - appeal dismissed
    2 Whitehead Place, Bradford
    “it appears that the Council has a significant shortfall in its housing land supply”
  7. Five years not shownDisputed19 July 2024 - appeal dismissed
    Land off Pasture Avenue, Oakworth, Keighley
    “it appears that the Council is unable to demonstrate a five-year housing land supply (5YHLS) as required by national policy”
  8. Five years not shownDisputed28 May 2024 - appeal dismissed
    Site Of Former Unit 18 Manywells Industrial Estate, Manywells Brow, Cullingworth, Bradford
    “The Council has confirmed that it currently has a 2.08 year supply of deliverable housing sites and consequently paragraph 11(d) of the Framework should be applied.”
    Figures given: council 2.08 years. Decision 3336321

Showing the 8 most recent of 13 decisions in Bradford that dealt with land supply. Planther searches and reads all of them for a site.

Housing Delivery Test

The Housing Delivery Test compares the homes built in a council's area over three years with the number needed. Bradford scored 56% in the 2025 measurement, published on 17 August 2026. The consequence listed in the government's results is: Presumption in favour of sustainable development.

YearHomes neededHomes delivered
2022 to 20232,3061,044
2023 to 20242,2351,418
2024 to 20252,2321,311

Source: Housing Delivery Test 2025 measurement. Every council's result: Housing Delivery Test results.

Local plan

The development plan is the Bradford District Core Strategy DPD (2017), Bradford City Centre Area Action Plan (2017), Shipley and Canal Road Corridor Area Action Plan (2017), Bradford Waste Management DPD (2017), Replacement Unitary Development Plan 2005 - saved policies and Nine made neighbourhood plans, adopted on 12 December 2017.

Nine made neighbourhood plans, the newest Bingley (July 2026); Baildon has been submitted for examination.

The Bradford District Local Plan 2025-2043

Being prepared under the plan-making system in place before 2026.

Now at regulation 19 consultation, step 3 of 7. Adoption expected: 2028.

  1. Early preparation
  2. Regulation 18 consultationFeb 2021
  3. NowRegulation 19 consultation19 Oct 2026
  4. Submitted31 Dec 2026
  5. Examination hearings
  6. Main modifications
  7. Adoption2028
  1. Early preparation
  2. Regulation 18 consultationFeb 2021
  3. Regulation 19 consultationNow19 Oct 2026
  4. Submitted31 Dec 2026
  5. Examination hearings
  6. Main modifications
  7. Adoption2028

The West Yorkshire Mass Transit Spatial Development Framework

Being prepared under the plan-making system in place before 2026.

Now at regulation 19 consultation, step 3 of 7.

  1. Early preparation
  2. Regulation 18 consultation29 Jan 2026
  3. NowRegulation 19 consultation4 Aug 2026
  4. Submitted31 Dec 2026
  5. Examination hearings
  6. Main modifications
  7. Adoption
  1. Early preparation
  2. Regulation 18 consultation29 Jan 2026
  3. Regulation 19 consultationNow4 Aug 2026
  4. Submitted31 Dec 2026
  5. Examination hearings
  6. Main modifications
  7. Adoption

Dates from the council's published timetable, its local development scheme.

Source: the council's local plan pages. Checked 2026-11-12 (7 days ago). Every council: where each local plan has got to.

Planning appeals

Since 2016, inspectors have decided 1,024 appeals against Bradford's decisions and allowed 267 of them (26%), against 31% across all councils. For major schemes, 2 of 8 were allowed (25%, against 50% across all councils).

YearDecidedAllowedShare allowed
201911132 (29%)
20209618 (19%)
202110532 (30%)
202212536 (29%)
20237916 (20%)
20246914 (20%)
202512628 (22%)
20266321 (33%)

Decided means allowed, dismissed or split, with a decision date; a split decision counts as decided but not allowed. From the Planning Inspectorate's published decisions.

Bradford's own pages

Land supply around Bradford

Barnsley: 2.9 yearsBassetlaw: 5.31 yearsBlackburn with Darwen: 5.7 yearsBolton: 3.61 yearsBradford: 3.59 yearsBurnley: 12.3 yearsBury: 4.3 yearsCalderdale: 3.89 yearsChorley: 3.4 yearsCumberland: 2.5 yearsDoncaster: 6.35 yearsEast Riding of Yorkshire: No current figure publishedFylde: 4.35 yearsHigh Peak: 2.47 yearsHyndburn: 5.91 yearsKirklees: 4.18 yearsKnowsley: 4.68 yearsLancaster: 2 yearsLeeds: 6.4 yearsManchester: No current figure publishedNorth Lincolnshire: No current figure publishedNorth Yorkshire: 2.26 yearsOldham: 6.7 yearsPendle: 5.32 yearsPreston: 5.48 yearsRibble Valley: 2.24 yearsRochdale: 5.2 yearsRossendale: 5.3 yearsRotherham: 4.4 yearsSalford: 7.1 yearsSheffield: No current figure publishedSouth Ribble: 5.53 yearsSt Helens: 6.07 yearsStockport: 1.77 yearsTameside: 5.35 yearsTrafford: 6.6 yearsWakefield: 5.5 yearsWarrington: 5.14 yearsWest Lancashire: 2.49 yearsWestmorland and Furness: 3.17 yearsWigan: 5.45 yearsWyre: 8.36 yearsYork: No current figure published
6 years or more5 to 6 years4 to 5 years, or says it cannot show fiveUnder 4 yearsNo current figure published

Each council's own latest figure. The whole country: land supply map of England.

About this page

Planther keeps track of every council's plan, land supply position and appeal record, and rebuilds this page every night from what it holds. Figures are the council's own unless they are marked as an inspector's. If something here is wrong, email hello@planther.co.uk and we will put it right.

See Planther at work in Bradford

Ask Planther about a site and it does the research: the council's position, the appeals that matter, and a first draft, each point with its source. Here it answers a question about Bradford from the figures on this page.

Book a demo

We will show you round Planther, then set you up with a trial so you can try it on your own work. We can usually have you, or your whole firm, up and running the same day.

Bringing a whole firm? We can work to your own contract and data processing agreement, and invoice you directly.