Merton Council says it can show a 5.2-year supply of housing land, at 1 April 2025, measured against Merton Local Plan 2024 stepped housing target (Policy H11.1): 4,590 homes over the five years, including demolitions for the estate regenerations, with no buffer added. The plan was adopted in November 2024, so its requirement applies rather than local housing need.
The most recent appeal decision that dealt with land supply, on 29 September 2025, found the council could show five years. Before that, inspectors found it could not, most recently on 24 July 2024.
It scored 63% in the 2025 Housing Delivery Test, and the government's results list the presumption in favour of sustainable development as the consequence.
Its local plan, the London Plan 2021 (Greater London Authority), was adopted on 20 November 2024.
Updated 2026-11-17 (2 days ago). Every figure links to where it comes from.