North Warwickshire: housing land supply, local plan and appeals

North Warwickshire Council says it can show a 1.5-year supply of housing land, at 31 March 2025, measured against Local Plan 2021 requirement (479 a year, 9,598 homes 2011-2033) plus 3,620 shortfall since 2011, short of the five years national policy asks for.

The four most recent appeal decisions that dealt with land supply, from 5 March 2026 to 12 November 2026, all found the council could not show five years. Before that, inspectors found it could, most recently on 28 March 2025.

It scored 164% in the 2025 Housing Delivery Test, with no consequence listed.

Its local plan, the North Warwickshire Local Plan 2021, was adopted on 29 September 2021. A replacement, the North Warwickshire Local Plan 2026, is at Regulation 19.

Updated 2026-11-17 (2 days ago). Every figure links to where it comes from.

Five-year housing land supply

North Warwickshire Council's latest published position is a 1.5-year supply of deliverable housing land for the period 2025/26 to 2029/30, made up of 2,207 homes it expects on deliverable sites. It is measured against Local Plan 2021 requirement (479 a year, 9,598 homes 2011-2033) plus 3,620 shortfall since 2011.

This is the latest figure the council has published. Its base date is 31 March 2025, more than 18 months ago.

Other councils in the West Midlands

Each council's own latest figure; base dates differ. All councils are on the land supply map of England.

Source: the council's land supply statement, published Annual Monitoring Report 2024/2025. Checked 2026-11-02 (2 weeks ago).

What inspectors found at appeal

A council's own land supply figure is often tested at appeal. These are the most recent appeal decisions in North Warwickshire where the inspector dealt with land supply, and what each one found.

  1. Five years not shownDisputed12 November 2026 - appeal dismissed
    Land Opposite Village Hall, Station Road, Whitacre Heath
    “The Council cannot demonstrate a 5 year supply of deliverable housing land”
  2. Five years not shownNot disputed30 July 2026 - appeal dismissed
    Land 120m North East of Ridley House, Ridley Lane, Nether Whitacre, Warwickshire
    “The Council advises that it cannot currently demonstrate a 5 year supply of deliverable housing land.”
  3. Five years not shownDisputed22 June 2026 - appeal allowed
    Land Between 10 And 32, Birmingham Road, Whitacre Heath
    “the Council cannot currently demonstrate a five-year supply”
    Figures given: council 2.2 years. Decision 6004388
  4. Five years not shownDisputed5 March 2026 - appeal allowed
    Land north west of Newton Regis Village Hall, Austrey Lane, Newton Regis, Warwickshire
    “the Council can only demonstrate a housing land supply of no more than 2.2 years”
    Figures given: inspector 2.2 years. Decision 3371147
  5. Five years shownNot disputed28 March 2025 - appeal dismissed
    Land To Rear Of 1 - 3 Birmingham Road, Ansley, NUNEATON
    “North Warwickshire has evidenced a housing land supply of 5.1 years”
    Figures given: council 5.1 years. Decision 3356485
  6. Five years shownNot disputed3 April 2023 - appeal dismissed
    Land opposite Delves Field Stables, Boulters Lane, Wood End, Warwickshire
    “the Council's housing land supply position of deliverable sites in excess of 5 years”

Housing Delivery Test

The Housing Delivery Test compares the homes built in a council's area over three years with the number needed. North Warwickshire scored 164% in the 2025 measurement, published on 17 August 2026. The consequence listed in the government's results is: None.

YearHomes neededHomes delivered
2022 to 2023176162
2023 to 2024168439
2024 to 2025163230

Source: Housing Delivery Test 2025 measurement. Every council's result: Housing Delivery Test results.

Local plan

The development plan is the North Warwickshire Local Plan 2021, Warwickshire Minerals Local Plan 2018-2032 (Warwickshire County Council), Warwickshire Waste Core Strategy 2013-2028 (Warwickshire County Council) and Ten made neighbourhood plans, adopted on 29 September 2021, covering 2011 to 2033. It replaced 2 earlier plans, including the North Warwickshire Core Strategy 2014.

Ten made neighbourhood plans, most recently Polesworth (2025); Austrey is modifying its plan and four more areas are designated.

The North Warwickshire Local Plan 2026

Being prepared under the plan-making system in place before 2026.

Now at regulation 19 consultation, step 3 of 7.

  1. Early preparation28 Nov 2025
  2. Regulation 18 consultation
  3. NowRegulation 19 consultation16 Oct 2026
  4. SubmittedDec 2026
  5. Examination hearings
  6. Main modifications
  7. Adoption
  1. Early preparation28 Nov 2025
  2. Regulation 18 consultation
  3. Regulation 19 consultationNow16 Oct 2026
  4. SubmittedDec 2026
  5. Examination hearings
  6. Main modifications
  7. Adoption

Dates from the council's published timetable, its local development scheme.

Source: the council's local plan pages. Checked 2026-11-02 (2 weeks ago). Every council: where each local plan has got to.

Planning appeals

Since 2016, inspectors have decided 154 appeals against North Warwickshire's decisions and allowed 52 of them (34%), against 31% across all councils. For major schemes, 9 of 15 were allowed (60%, against 50% across all councils).

YearDecidedAllowedShare allowed
2019105 (50%)
2020110 (0%)
2021194 (21%)
202272 (29%)
2023111 (9%)
2024278 (30%)
202593 (33%)
2026107 (70%)

Decided means allowed, dismissed or split, with a decision date; a split decision counts as decided but not allowed. From the Planning Inspectorate's published decisions.

North Warwickshire's own pages

Land supply around North Warwickshire

Amber Valley: 5.8 yearsBirmingham: 6.45 yearsBlaby: 2.78 yearsBromsgrove: 2.24 yearsBroxtowe: No current figure publishedCannock Chase: 5 yearsCentral Bedfordshire: 3.93 yearsCharnwood: 3.56 yearsCherwell: 3.1 yearsCheshire East: 3.3 yearsCoventry: No current figure publishedDerby: 2.39 yearsDerbyshire Dales: No current figure publishedDudley: No current figure publishedEast Staffordshire: 5.06 yearsErewash: 1.6 yearsGedling: 3.73 yearsHarborough: 3.1 yearsHerefordshire: 2.81 yearsHinckley and Bosworth: 4.47 yearsLeicester: No current figure publishedLichfield: 3.5 yearsMalvern Hills: 5.48 yearsMelton: 7.6 yearsMilton Keynes: 5.47 yearsNewark and Sherwood: 4.02 yearsNewcastle-under-Lyme: No current figure publishedNorth Kesteven: 7.1 yearsNorth Northamptonshire: 4.35 yearsNorth Warwickshire: 1.5 yearsNorth West Leicestershire: 5.1 yearsNottingham: 6.57 yearsNuneaton and Bedworth: 10.2 yearsOadby and Wigston: 6.68 yearsRedditch: No current figure publishedRugby: 3.4 yearsRushcliffe: 5.1 yearsRutland: 4.34 yearsSandwell: 1.86 yearsShropshire: 4.61 yearsSolihull: No current figure publishedSouth Derbyshire: 5.27 yearsSouth Kesteven: 4.07 yearsSouth Staffordshire: 0.87 yearsStafford: No current figure publishedStaffordshire Moorlands: 2.95 yearsStoke-on-Trent: 3.73 yearsStratford-on-Avon: 2.43 yearsTamworth: 1.6 yearsTelford and Wrekin: 6.02 yearsWalsall: 2 yearsWarwick: No current figure publishedWest Northamptonshire: No current figure publishedWolverhampton: Says it cannot show five yearsWorcester: 5.48 yearsWychavon: 5.48 yearsWyre Forest: 8.8 years
6 years or more5 to 6 years4 to 5 years, or says it cannot show fiveUnder 4 yearsNo current figure published

Each council's own latest figure. The whole country: land supply map of England.

About this page

Planther keeps track of every council's plan, land supply position and appeal record, and rebuilds this page every night from what it holds. Figures are the council's own unless they are marked as an inspector's. If something here is wrong, email hello@planther.co.uk and we will put it right.

See Planther at work in North Warwickshire

Ask Planther about a site and it does the research: the council's position, the appeals that matter, and a first draft, each point with its source. Here it answers a question about North Warwickshire from the figures on this page.

Book a demo

We will show you round Planther, then set you up with a trial so you can try it on your own work. We can usually have you, or your whole firm, up and running the same day.

Bringing a whole firm? We can work to your own contract and data processing agreement, and invoice you directly.