Wyre Forest: housing land supply, local plan and appeals

Wyre Forest Council says it can show a 8.8-year supply of housing land, at 1 April 2026, measured against the Local Plan requirement of 276 homes a year (Policy SP1) plus a care-home (C2) requirement of 64 dwellings, because the plan was adopted in the last five years.

The most recent appeal decision that dealt with land supply, on 14 May 2026, found the council could show five years. Before that, inspectors found it could not, most recently on 5 June 2025.

It scored 212% in the 2025 Housing Delivery Test, with no consequence listed.

Its local plan, the Wyre Forest District Local Plan 2016-2036, was adopted on 26 April 2022. A replacement, the Wyre Forest Local Plan (new system), is at Gateway 1, with adoption expected in January 2029.

Updated 2026-11-17 (2 days ago). Every figure links to where it comes from.

Five-year housing land supply

Wyre Forest Council's latest published position is a 8.8-year supply of deliverable housing land for the five years from 1 April 2026 (2026/27 to 2030/31). It is measured against the Local Plan requirement of 276 homes a year (Policy SP1) plus a care-home (C2) requirement of 64 dwellings, because the plan was adopted in the last five years.

The standard method would give a local housing need of 584 homes a year, but the report uses the adopted plan's 276 because the plan is under five years old. The report applies a 5% buffer on the strength of a 185% Housing Delivery Test result. It also quotes the NPPF rule for a 20% buffer from 1 July 2026 (for decisions only) but does not say whether it applies.

Other councils in the West Midlands

Each council's own latest figure; base dates differ. All councils are on the land supply map of England.

Source: the council's land supply statement, published April 2026. Checked 2026-10-05 (6 weeks ago).

What inspectors found at appeal

A council's own land supply figure is often tested at appeal. These are the most recent appeal decisions in Wyre Forest where the inspector dealt with land supply, and what each one found.

  1. Five years shownNot disputed14 May 2026 - appeal dismissed
    Grove Farmhouse, Drayton Road, Belbroughton
    “The appellant has not contested the Council stance that it has a 5-year supply of deliverable housing sites”
    Figures given: council 5 years. Decision 6004729
  2. Five years not shownNot disputed5 June 2025 - appeal allowed
    Land at Drakelow Lane, Wolverley, Worcestershire
    “it is now common ground, in light of recent appeal decisions at Curslow Lane, Shenstone , that the Council is currently unable to demonstrate a 5-year supply of deliverable sites.”

Housing Delivery Test

The Housing Delivery Test compares the homes built in a council's area over three years with the number needed. Wyre Forest scored 212% in the 2025 measurement, published on 17 August 2026. The consequence listed in the government's results is: None.

YearHomes neededHomes delivered
2022 to 2023232516
2023 to 2024228368
2024 to 2025211537

Source: Housing Delivery Test 2025 measurement. Every council's result: Housing Delivery Test results.

Local plan

The development plan is the Wyre Forest District Local Plan 2016-2036, adopted on 26 April 2022, covering 2016 to 2036. It replaced 3 earlier plans, including the Core Strategy (December 2010).

Two made neighbourhood plans (Chaddesley Corbett, Churchill and Blakedown); Bewdley is emerging at Regulation 15; Upper Arley and Cookley and Caunsall are designated areas with no plan yet.

The Wyre Forest Local Plan (new system)

Being prepared under the plan-making system introduced in 2026, which runs each plan through three gateways in about 30 months.

Now at gateway 1, step 3 of 9. Adoption expected in January 2029, 2 years and 2 months away.

  1. Notice of intention8 Apr 2026
  2. Scoping consultation7 July 2026
  3. NowGateway 131 Aug 2026
  4. Content and evidence consultationJan 2027
  5. Gateway 2Apr 2027
  6. Plan consultationJune 2027
  7. Gateway 3Mar 2028
  8. ExaminationJuly 2028
  9. AdoptionJan 2029
  1. Notice of intention8 Apr 2026
  2. Scoping consultation7 July 2026
  3. Gateway 1Now31 Aug 2026
  4. Content and evidence consultationJan 2027
  5. Gateway 2Apr 2027
  6. Plan consultationJune 2027
  7. Gateway 3Mar 2028
  8. ExaminationJuly 2028
  9. AdoptionJan 2029

Dates from the council's published timetable, its local development scheme.

Source: the council's local plan pages. Checked 2026-10-05 (6 weeks ago). Every council: where each local plan has got to.

Planning appeals

Since 2016, inspectors have decided 201 appeals against Wyre Forest's decisions and allowed 80 of them (40%), against 31% across all councils. For major schemes, 3 of 7 were allowed (43%, against 50% across all councils).

YearDecidedAllowedShare allowed
2019229 (41%)
20202912 (41%)
2021115 (45%)
2022187 (39%)
2023168 (50%)
20242611 (42%)
20252512 (48%)
2026154 (27%)

Decided means allowed, dismissed or split, with a decision date; a split decision counts as decided but not allowed. From the Planning Inspectorate's published decisions.

Wyre Forest's own pages

Land supply around Wyre Forest

Birmingham: 6.45 yearsBromsgrove: 2.24 yearsCannock Chase: 5 yearsCotswold: 1.8 yearsCoventry: No current figure publishedDudley: No current figure publishedHerefordshire: 2.81 yearsHinckley and Bosworth: 4.47 yearsLichfield: 3.5 yearsMalvern Hills: 5.48 yearsNorth Warwickshire: 1.5 yearsNorth West Leicestershire: 5.1 yearsRedditch: No current figure publishedSandwell: 1.86 yearsShropshire: 4.61 yearsSolihull: No current figure publishedSouth Staffordshire: 0.87 yearsStratford-on-Avon: 2.43 yearsTamworth: 1.6 yearsTelford and Wrekin: 6.02 yearsWalsall: 2 yearsWarwick: No current figure publishedWolverhampton: Says it cannot show five yearsWorcester: 5.48 yearsWychavon: 5.48 yearsWyre Forest: 8.8 years
6 years or more5 to 6 years4 to 5 years, or says it cannot show fiveUnder 4 yearsNo current figure published

Each council's own latest figure. The whole country: land supply map of England.

About this page

Planther keeps track of every council's plan, land supply position and appeal record, and rebuilds this page every night from what it holds. Figures are the council's own unless they are marked as an inspector's. If something here is wrong, email hello@planther.co.uk and we will put it right.

See Planther at work in Wyre Forest

Ask Planther about a site and it does the research: the council's position, the appeals that matter, and a first draft, each point with its source. Here it answers a question about Wyre Forest from the figures on this page.

Book a demo

We will show you round Planther, then set you up with a trial so you can try it on your own work. We can usually have you, or your whole firm, up and running the same day.

Bringing a whole firm? We can work to your own contract and data processing agreement, and invoice you directly.