Walsall: housing land supply, local plan and appeals

Walsall Council says it can show a 2-year supply of housing land, at 1 April 2025, measured against local housing need by the standard method (1,172 homes a year, 7,032 over five years with a 20% buffer), because the Black Country Core Strategy is more than five years old, short of the five years national policy asks for.

The seven most recent appeal decisions that dealt with land supply, from 24 March 2023 to 2 June 2026, all found the council could not show five years.

It scored 56% in the 2025 Housing Delivery Test, and the government's results list the presumption in favour of sustainable development as the consequence.

Its local plan, the Black Country Core Strategy (2011), was adopted on 7 January 2019. A replacement, the Walsall Borough Local Plan, is at Regulation 19.

Updated 2026-11-17 (2 days ago). Every figure links to where it comes from.

Five-year housing land supply

Walsall Council's latest published position is a 2-year supply of deliverable housing land for the April 2025 position (document published November 2025), made up of 2,769 homes it expects on deliverable sites. It is measured against local housing need by the standard method (1,172 homes a year, 7,032 over five years with a 20% buffer), because the Black Country Core Strategy is more than five years old.

The council gives 'approximately two years' in words and no exact figure; 2,769 divided by 1,406 a year is about 1.97. The 20% buffer reflects the council's reading of earlier Housing Delivery Test results. The figure is a land availability assessment position as at April 2025, not a formal five-year statement, and local housing need was 1,216 homes a year in May 2026.

This is the latest figure the council has published. Its base date is 1 April 2025, more than 18 months ago.

Other councils in the West Midlands

Each council's own latest figure; base dates differ. All councils are on the land supply map of England.

Source: the council's land supply statement, published November 2025. Checked 2026-10-05 (6 weeks ago).

What inspectors found at appeal

A council's own land supply figure is often tested at appeal. These are the most recent appeal decisions in Walsall where the inspector dealt with land supply, and what each one found.

  1. Five years not shownNot disputed2 June 2026 - appeal dismissed
    26 Haley St, Short Heath, Willenhall, West Mids
    “The submissions indicate the Council is currently able to demonstrate less than 2 years of housing land supply against the 5 year requirement. This is a substantial shortfall.”
  2. Five years not shownNot disputed2 April 2026 - appeal dismissed
    ENERGY HEALTH & FITNESS 9-10A THE BIRDGE, WALSALL
    “The Council cannot demonstrate a sufficient supply of deliverable housing sites and has failed the Housing Delivery Test.”
  3. Five years not shownDisputed28 May 2025 - appeal dismissed
    Land rear of 13, 13A and 15 Buchanan Road, Walsall
    “As of April 2024, the known supply (after discount) of 3304 dwellings is below the five year (plus 20% buffer) requirement of 5436 dwellings and equates to only sufficient for 3 years, a significant shortfall.”
    Figures given: council 3 years. Decision 3354771
  4. Five years not shownNot disputed2 December 2024 - appeal dismissed
    Pelsall Villa Football Club, Walsall Road, Pelsall
    “It would also enable the release of about 47 houses back into the housing market at a time when the Council is unable to demonstrate a five year housing land supply”
  5. Five years not shownNot disputed26 January 2024 - appeal dismissed
    Land adj 12 Herberts Park Road, Walsall
    “The council cannot demonstrate a 5 year supply of deliverable housing land.”
  6. Five years not shownNot disputed3 November 2023 - appeal allowed
    Little Aston Road, Aldridge, Walsall
    “the Council is currently unable to demonstrate a five-year supply of deliverable housing land”
  7. Five years not shownNot disputed24 March 2023 - appeal dismissed
    6 Linden Lane, Willenhall
    “The Council has confirmed that it is currently unable to demonstrate a five year supply of housing land”

Housing Delivery Test

The Housing Delivery Test compares the homes built in a council's area over three years with the number needed. Walsall scored 56% in the 2025 measurement, published on 17 August 2026. The consequence listed in the government's results is: Presumption in favour of sustainable development.

YearHomes neededHomes delivered
2022 to 2023909453
2023 to 2024907388
2024 to 2025906684

Source: Housing Delivery Test 2025 measurement. Every council's result: Housing Delivery Test results.

Local plan

The development plan is the Black Country Core Strategy (2011), Walsall Site Allocations Document (2019), Walsall Unitary Development Plan (saved policies) and Walsall Town Centre Area Action Plan, adopted on 7 January 2019.

The Walsall Borough Local Plan

Being prepared under the plan-making system in place before 2026.

Now at regulation 19 consultation, step 3 of 7.

  1. Early preparation2024
  2. Regulation 18 consultation7 Nov 2025
  3. NowRegulation 19 consultation21 Sep 2026
  4. SubmittedDec 2026
  5. Examination hearings
  6. Main modifications
  7. Adoption
  1. Early preparation2024
  2. Regulation 18 consultation7 Nov 2025
  3. Regulation 19 consultationNow21 Sep 2026
  4. SubmittedDec 2026
  5. Examination hearings
  6. Main modifications
  7. Adoption

Dates from the council's published timetable, its local development scheme.

Source: the council's local plan pages. Checked 2026-10-05 (6 weeks ago). Every council: where each local plan has got to.

Planning appeals

Since 2016, inspectors have decided 320 appeals against Walsall's decisions and allowed 96 of them (30%), against 31% across all councils. For major schemes, 6 of 7 were allowed (86%, against 50% across all councils).

YearDecidedAllowedShare allowed
2019379 (24%)
2020208 (40%)
2021299 (31%)
2022245 (21%)
20233011 (37%)
2024317 (23%)
20253213 (41%)
20263810 (26%)

Decided means allowed, dismissed or split, with a decision date; a split decision counts as decided but not allowed. From the Planning Inspectorate's published decisions.

Walsall's own pages

Land supply around Walsall

Birmingham: 6.45 yearsBromsgrove: 2.24 yearsCannock Chase: 5 yearsCoventry: No current figure publishedDudley: No current figure publishedEast Staffordshire: 5.06 yearsHinckley and Bosworth: 4.47 yearsLichfield: 3.5 yearsNorth Warwickshire: 1.5 yearsNorth West Leicestershire: 5.1 yearsNuneaton and Bedworth: 10.2 yearsSandwell: 1.86 yearsShropshire: 4.61 yearsSolihull: No current figure publishedSouth Derbyshire: 5.27 yearsSouth Staffordshire: 0.87 yearsStafford: No current figure publishedTamworth: 1.6 yearsTelford and Wrekin: 6.02 yearsWalsall: 2 yearsWolverhampton: Says it cannot show five yearsWyre Forest: 8.8 years
6 years or more5 to 6 years4 to 5 years, or says it cannot show fiveUnder 4 yearsNo current figure published

Each council's own latest figure. The whole country: land supply map of England.

About this page

Planther keeps track of every council's plan, land supply position and appeal record, and rebuilds this page every night from what it holds. Figures are the council's own unless they are marked as an inspector's. If something here is wrong, email hello@planther.co.uk and we will put it right.

See Planther at work in Walsall

Ask Planther about a site and it does the research: the council's position, the appeals that matter, and a first draft, each point with its source. Here it answers a question about Walsall from the figures on this page.

Book a demo

We will show you round Planther, then set you up with a trial so you can try it on your own work. We can usually have you, or your whole firm, up and running the same day.

Bringing a whole firm? We can work to your own contract and data processing agreement, and invoice you directly.