Rugby: housing land supply, local plan and appeals

Rugby Council says it can show a 3.4-year supply of housing land, at 1 April 2025, measured against local housing need (Local Plan more than five years old), short of the five years national policy asks for.

The six most recent appeal decisions that dealt with land supply, from 27 May 2025 to 16 November 2026, all found the council could not show five years. Before that, inspectors found it could, most recently on 12 March 2024.

It scored 187% in the 2025 Housing Delivery Test, with no consequence listed.

Its local plan, the Rugby Borough Local Plan 2011-2031, was adopted on 4 June 2019. A replacement, the Rugby Borough Local Plan 2025-2042, is at examination.

Updated 2026-11-17 (2 days ago). Every figure links to where it comes from.

Five-year housing land supply

Rugby Council's latest published position is a 3.4-year supply of deliverable housing land for the period 2025 to 2030. It is measured against local housing need (Local Plan more than five years old).

This is the latest figure the council has published. Its base date is 1 April 2025, more than 18 months ago.

Other councils in the West Midlands

Each council's own latest figure; base dates differ. All councils are on the land supply map of England.

Source: the council's land supply statement, published 2026-03-27. Checked 2026-10-29 (3 weeks ago).

What inspectors found at appeal

A council's own land supply figure is often tested at appeal. These are the most recent appeal decisions in Rugby where the inspector dealt with land supply, and what each one found.

  1. Five years not shownNot disputed16 November 2026 - appeal allowed
    Millfield, Mill Row, Wolvey
    “The Council cites a housing land supply figure of 4.16 years. Given this information, there is a clear evidenced need for housing”
    Figures given: council 4.16 years. Decision 6011478
  2. Five years not shownNot disputed13 August 2026 - appeal dismissed
    Land to the north of the Old Dairy, Coton House Estate, Rugby
    “The submitted evidence indicates that the Council is unable to demonstrate a five-year supply of deliverable housing sites in accordance with the Framework”
  3. Five years not shownNot disputed22 May 2026 - appeal dismissed
    Land East of Rugby Road, Clifton-upon-Dunsmore, Rugby
    “As this falls short of the required five-year supply, the policies most important for determining the scheme - namely Polices DS1 and GP2 of the LP - are deemed out-of-date”
    Figures given: council 3.4 years, inspector 3.4 years. Decision 6003106
  4. Five years not shownDisputed13 March 2026 - appeal dismissed
    Land North of Rounds Gardens, Rugby
    “Given my findings above, I calculate that a total of 507 units should be removed from the Council's posited supply, leaving a total supply of 2,270 homes for the five-year period. This leads to a supply of approximately 3.4 years.”
    Figures given: council 4.16 years, appellant 2.04 years, inspector 3.4 years. Decision 3373251
  5. Five years not shownNot disputed23 December 2025 - appeal dismissed
    Saxon Fields Equestrian, Lilbourne Road, Clifton Upon Dunsmore, Rugby
    “Both parties agree that the Council is unable to demonstrate a five year housing land supply with the quoted supply being 4.6 years, which is a limited shortfall but still a shortfall”
    Figures given: council 4.6 years, appellant 4.6 years. Decision 6000588
  6. Five years not shownNot disputed27 May 2025 - appeal dismissed
    Land West of High Street, Ryton on Dunsmore
    “The Council have confirmed that it can no longer demonstrate a five-year housing land supply. The Council's updated position as of 1 April 2024 is a supply of 4.6 years.”
    Figures given: council 4.6 years. Decision 3359147
  7. Five years shownNot disputed12 March 2024 - appeal allowed
    Merlin Field Farm, Gibraltar Lane, Leamington Hastings, Rugby
    “The Council has confirmed it is able to demonstrate a five-year supply of deliverable housing sites”
  8. Five years shownNot disputed19 January 2024 - appeal dismissed
    Coventry Stadium, Rugby Road, Coventry
    “the Council is not required to demonstrate a five-year housing land supply as the adopted local plan is less than 5 years old. In fact, the Council has a 6.1-year supply of housing (as of 1 April 2023).”
    Figures given: council 6.1 years, inspector 6.1 years. Decision 3322013

Showing the 8 most recent of 9 decisions in Rugby that dealt with land supply. Planther searches and reads all of them for a site.

Housing Delivery Test

The Housing Delivery Test compares the homes built in a council's area over three years with the number needed. Rugby scored 187% in the 2025 measurement, published on 17 August 2026. The consequence listed in the government's results is: None.

YearHomes neededHomes delivered
2022 to 20235161,347
2023 to 2024506871
2024 to 2025525676

Source: Housing Delivery Test 2025 measurement. Every council's result: Housing Delivery Test results.

Local plan

The development plan is the Rugby Borough Local Plan 2011-2031 and Made neighbourhood plans, adopted on 4 June 2019, covering 2011 to 2031. It replaced the Rugby Core Strategy 2011.

Eight made neighbourhood plans; Newton and Biggin is in consultation until 13 November 2026.

The Rugby Borough Local Plan 2025-2042

Being prepared under the plan-making system in place before 2026.

Now at examination hearings, step 5 of 7.

  1. Early preparation
  2. Regulation 18 consultation24 Mar 2025
  3. Regulation 19 consultation30 Jan 2026
  4. Submitted27 Apr 2026
  5. NowExamination hearings17 Nov 2026
  6. Main modifications
  7. Adoption
  1. Early preparation
  2. Regulation 18 consultation24 Mar 2025
  3. Regulation 19 consultation30 Jan 2026
  4. Submitted27 Apr 2026
  5. Examination hearingsNow17 Nov 2026
  6. Main modifications
  7. Adoption

Dates from the council's published timetable, its local development scheme.

Source: the council's local plan pages. Checked 2026-10-29 (3 weeks ago). Every council: where each local plan has got to.

Planning appeals

Since 2016, inspectors have decided 198 appeals against Rugby's decisions and allowed 66 of them (33%), against 31% across all councils. For major schemes, 6 of 12 were allowed (50%, against 50% across all councils).

YearDecidedAllowedShare allowed
2019152 (13%)
2020218 (38%)
2021138 (62%)
2022174 (24%)
20232510 (40%)
2024178 (47%)
20252610 (38%)
2026121 (8%)

Decided means allowed, dismissed or split, with a decision date; a split decision counts as decided but not allowed. From the Planning Inspectorate's published decisions.

Rugby's own pages

Land supply around Rugby

Bedford: 3.35 yearsBirmingham: 6.45 yearsBlaby: 2.78 yearsBromsgrove: 2.24 yearsBuckinghamshire: 0.86 yearsCannock Chase: 5 yearsCentral Bedfordshire: 3.93 yearsCharnwood: 3.56 yearsCherwell: 3.1 yearsCotswold: 1.8 yearsCoventry: No current figure publishedDudley: No current figure publishedEast Staffordshire: 5.06 yearsForest of Dean: No current figure publishedHarborough: 3.1 yearsHerefordshire: 2.81 yearsHinckley and Bosworth: 4.47 yearsHuntingdonshire: 4.28 yearsLeicester: No current figure publishedLichfield: 3.5 yearsMalvern Hills: 5.48 yearsMelton: 7.6 yearsMilton Keynes: 5.47 yearsNorth Hertfordshire: 2.43 yearsNorth Northamptonshire: 4.35 yearsNorth Warwickshire: 1.5 yearsNorth West Leicestershire: 5.1 yearsNuneaton and Bedworth: 10.2 yearsOadby and Wigston: 6.68 yearsPeterborough: 4.38 yearsRedditch: No current figure publishedRugby: 3.4 yearsRushcliffe: 5.1 yearsRutland: 4.34 yearsSandwell: 1.86 yearsShropshire: 4.61 yearsSolihull: No current figure publishedSouth Derbyshire: 5.27 yearsSouth Holland: 4.6 yearsSouth Kesteven: 4.07 yearsSouth Staffordshire: 0.87 yearsStafford: No current figure publishedStratford-on-Avon: 2.43 yearsTamworth: 1.6 yearsTelford and Wrekin: 6.02 yearsTewkesbury: 3.65 yearsWalsall: 2 yearsWarwick: No current figure publishedWest Northamptonshire: No current figure publishedWest Oxfordshire: Says it cannot show five yearsWolverhampton: Says it cannot show five yearsWorcester: 5.48 yearsWychavon: 5.48 yearsWyre Forest: 8.8 years
6 years or more5 to 6 years4 to 5 years, or says it cannot show fiveUnder 4 yearsNo current figure published

Each council's own latest figure. The whole country: land supply map of England.

About this page

Planther keeps track of every council's plan, land supply position and appeal record, and rebuilds this page every night from what it holds. Figures are the council's own unless they are marked as an inspector's. If something here is wrong, email hello@planther.co.uk and we will put it right.

See Planther at work in Rugby

Ask Planther about a site and it does the research: the council's position, the appeals that matter, and a first draft, each point with its source. Here it answers a question about Rugby from the figures on this page.

Book a demo

We will show you round Planther, then set you up with a trial so you can try it on your own work. We can usually have you, or your whole firm, up and running the same day.

Bringing a whole firm? We can work to your own contract and data processing agreement, and invoice you directly.