Wigan: housing land supply, local plan and appeals

Wigan Council says it can show a 5.45-year supply of housing land, at 1 April 2026, measured against Places for Everyone housing requirement (972 a year to 2030, stepping to 1,025 in 2030/31); 5% buffer because the 2025 Housing Delivery Test was above 85%.

The three most recent appeal decisions that dealt with land supply, from 13 August 2025 to 3 June 2026, all found the council could show five years.

It scored 153% in the 2025 Housing Delivery Test, with no consequence listed.

Its local plan, the Places for Everyone Joint Development Plan Document (2024), was adopted on 21 March 2024. A replacement, the Wigan Borough Local Plan, is at Regulation 19.

Updated 2026-11-17 (2 days ago). Every figure links to where it comes from.

Five-year housing land supply

Wigan Council's latest published position is a 5.45-year supply of deliverable housing land for the period 2026/27 to 2030/31, made up of 5,627 homes it expects on deliverable sites. It is measured against Places for Everyone housing requirement (972 a year to 2030, stepping to 1,025 in 2030/31); 5% buffer because the 2025 Housing Delivery Test was above 85%.

Other councils in the North West

Each council's own latest figure; base dates differ. All councils are on the land supply map of England.

Source: the council's land supply statement, published 2026-08. Checked 2026-10-28 (3 weeks ago).

What inspectors found at appeal

A council's own land supply figure is often tested at appeal. These are the most recent appeal decisions in Wigan where the inspector dealt with land supply, and what each one found.

  1. Five years shownNot disputed3 June 2026 - appeal dismissed
    Land east of Bramblemead, Bramblemead, Leigh
    “Therefore, the criteria set out in paragraph 155 (b) is not met.”
    Figures given: council 6.09 years. Decision 6004698
  2. Five years shownNot disputed30 September 2025 - appeal dismissed
    Shams Farm Shakerley Lane, Atherton, MANCHESTER
    “The Council are able to demonstrate a five-year supply of deliverable housing sites. The evidence indicates that a supply of 5.41 years is available.”
    Figures given: council 5.41 years, inspector 5.41 years. Decision 3365202
  3. Five years shownDisputed13 August 2025 - appeal dismissed
    Astley House, Johnson Street, Tyldesley, Manchester
    “demonstrate that the Council has a housing land supply greater than 5 years”
    Figures given: council 5.41 years, appellant 3.75 years, inspector 5 years. Decision 3364633

Housing Delivery Test

The Housing Delivery Test compares the homes built in a council's area over three years with the number needed. Wigan scored 153% in the 2025 measurement, published on 17 August 2026. The consequence listed in the government's results is: None.

YearHomes neededHomes delivered
2022 to 20238141,408
2023 to 20248141,146
2024 to 20258031,171

Source: Housing Delivery Test 2025 measurement. Every council's result: Housing Delivery Test results.

Local plan

The development plan is the Places for Everyone Joint Development Plan Document (2024), Wigan Local Plan Core Strategy (2013) - remaining policies, Wigan Replacement Unitary Development Plan (2006) - saved policies, Greater Manchester Joint Waste Development Plan Document (2012) and Greater Manchester Joint Minerals Plan (2013), adopted on 21 March 2024, covering 2022 to 2039. It replaced 2 earlier plans, including the parts of the Wigan Local Plan Core Strategy.

Three made neighbourhood plans: Standish, Golborne and Lowton West, and Abram.

The Wigan Borough Local Plan

Being prepared under the plan-making system in place before 2026.

Now at regulation 19 consultation, step 3 of 7. Adoption expected: late 2027 / early 2028.

  1. Early preparation
  2. Regulation 18 consultation30 Apr 2025
  3. NowRegulation 19 consultation9 Sep 2026
  4. SubmittedDec 2026
  5. Examination hearings2027
  6. Main modifications
  7. Adoptionlate 2027 / early 2028
  1. Early preparation
  2. Regulation 18 consultation30 Apr 2025
  3. Regulation 19 consultationNow9 Sep 2026
  4. SubmittedDec 2026
  5. Examination hearings2027
  6. Main modifications
  7. Adoptionlate 2027 / early 2028

Dates from the council's published timetable, its local development scheme.

Source: the council's local plan pages. Checked 2026-10-28 (3 weeks ago). Every council: where each local plan has got to.

Planning appeals

Since 2016, inspectors have decided 246 appeals against Wigan's decisions and allowed 56 of them (23%), against 31% across all councils.

YearDecidedAllowedShare allowed
2019214 (19%)
2020266 (23%)
20213712 (32%)
2022216 (29%)
2023226 (27%)
2024334 (12%)
20254411 (25%)
2026213 (14%)

Decided means allowed, dismissed or split, with a decision date; a split decision counts as decided but not allowed. From the Planning Inspectorate's published decisions.

Wigan's own pages

Land supply around Wigan

Blackburn with Darwen: 5.7 yearsBlackpool: 2.1 yearsBolton: 3.61 yearsBradford: 3.59 yearsBurnley: 12.3 yearsBury: 4.3 yearsCalderdale: 3.89 yearsCheshire East: 3.3 yearsCheshire West and Chester: 1.6 yearsChorley: 3.4 yearsFylde: 4.35 yearsHalton: No current figure publishedHigh Peak: 2.47 yearsHyndburn: 5.91 yearsKirklees: 4.18 yearsKnowsley: 4.68 yearsLiverpool: 5.64 yearsManchester: No current figure publishedNorth Yorkshire: 2.26 yearsOldham: 6.7 yearsPendle: 5.32 yearsPreston: 5.48 yearsRibble Valley: 2.24 yearsRochdale: 5.2 yearsRossendale: 5.3 yearsSalford: 7.1 yearsSefton: 3.34 yearsSouth Ribble: 5.53 yearsSt Helens: 6.07 yearsStockport: 1.77 yearsTameside: 5.35 yearsTrafford: 6.6 yearsWarrington: 5.14 yearsWest Lancashire: 2.49 yearsWigan: 5.45 yearsWirral: 6.63 yearsWyre: 8.36 years
6 years or more5 to 6 years4 to 5 years, or says it cannot show fiveUnder 4 yearsNo current figure published

Each council's own latest figure. The whole country: land supply map of England.

About this page

Planther keeps track of every council's plan, land supply position and appeal record, and rebuilds this page every night from what it holds. Figures are the council's own unless they are marked as an inspector's. If something here is wrong, email hello@planther.co.uk and we will put it right.

See Planther at work in Wigan

Ask Planther about a site and it does the research: the council's position, the appeals that matter, and a first draft, each point with its source. Here it answers a question about Wigan from the figures on this page.

Book a demo

We will show you round Planther, then set you up with a trial so you can try it on your own work. We can usually have you, or your whole firm, up and running the same day.

Bringing a whole firm? We can work to your own contract and data processing agreement, and invoice you directly.