Chesterfield: housing land supply, local plan and appeals

Chesterfield Council says it can show a 3.46-year supply of housing land, at 1 April 2026, measured against standard method local housing need (the 2020 Local Plan requirement of 240 homes a year is more than five years old), short of the five years national policy asks for.

The most recent appeal decision that dealt with land supply, on 2 February 2026, found the council could not show five years.

It scored 168% in the 2025 Housing Delivery Test, with no consequence listed.

Its local plan, the Chesterfield Borough Local Plan, was adopted on 15 July 2020. A replacement, the Chesterfield Borough Local Plan 2025 to 2044, is at Gateway 1, with adoption expected on 19 July 2028.

Updated 2026-11-17 (2 days ago). Every figure links to where it comes from.

Five-year housing land supply

Chesterfield Council's latest published position is a 3.46-year supply of deliverable housing land for the period 2026/27 to 2030/31, made up of 1,795 homes it expects on deliverable sites. It is measured against standard method local housing need (the 2020 Local Plan requirement of 240 homes a year is more than five years old).

Other councils in the East Midlands

Each council's own latest figure; base dates differ. All councils are on the land supply map of England.

Source: the council's land supply statement, published 2026-08. Checked 2026-10-04 (7 weeks ago).

What inspectors found at appeal

A council's own land supply figure is often tested at appeal. These are the most recent appeal decisions in Chesterfield where the inspector dealt with land supply, and what each one found.

  1. Five years not shownNot disputed2 February 2026 - appeal dismissed
    Former Tapton City Cottages, Tapton
    “The Council accepts that it cannot demonstrate a five year supply of deliverable housing sites, with supply stated to be 3.12 years.”
    Figures given: council 3.12 years. Decision 3369539

Housing Delivery Test

The Housing Delivery Test compares the homes built in a council's area over three years with the number needed. Chesterfield scored 168% in the 2025 measurement, published on 17 August 2026. The consequence listed in the government's results is: None.

YearHomes neededHomes delivered
2022 to 2023228370
2023 to 2024216386
2024 to 2025211345

Source: Housing Delivery Test 2025 measurement. Every council's result: Housing Delivery Test results.

Local plan

The development plan is the Chesterfield Borough Local Plan, Saved policies of the Derby and Derbyshire Waste Local Plan (2005) and Saved policies of the Derby and Derbyshire Minerals Local Plan (2000, altered 2002), adopted on 15 July 2020, covering 2018 to 2035.

The council says there are currently no neighbourhood plans in Chesterfield borough.

The Chesterfield Borough Local Plan 2025 to 2044

Being prepared under the plan-making system introduced in 2026, which runs each plan through three gateways in about 30 months.

Now at gateway 1, step 3 of 9. Adoption expected on 19 July 2028, 1 year and 8 months away.

  1. Notice of intention20 May 2026
  2. Scoping consultation15 June 2026
  3. NowGateway 121 Sep 2026
  4. Content and evidence consultation23 Nov 2026
  5. Gateway 226 Feb 2027
  6. Plan consultation26 July 2027
  7. Gateway 311 Oct 2027
  8. Examination8 Nov 2027
  9. Adoption19 July 2028
  1. Notice of intention20 May 2026
  2. Scoping consultation15 June 2026
  3. Gateway 1Now21 Sep 2026
  4. Content and evidence consultation23 Nov 2026
  5. Gateway 226 Feb 2027
  6. Plan consultation26 July 2027
  7. Gateway 311 Oct 2027
  8. Examination8 Nov 2027
  9. Adoption19 July 2028

Dates from the council's published timetable, its local development scheme.

Source: the council's local plan pages. Checked 2026-10-04 (7 weeks ago). Every council: where each local plan has got to.

Planning appeals

Since 2016, inspectors have decided 103 appeals against Chesterfield's decisions and allowed 32 of them (31%), against 31% across all councils.

YearDecidedAllowedShare allowed
2019123 (25%)
202062 (33%)
202131 (33%)
2022134 (31%)
2023135 (38%)
202472 (29%)
202583 (38%)
2026225 (23%)

Decided means allowed, dismissed or split, with a decision date; a split decision counts as decided but not allowed. From the Planning Inspectorate's published decisions.

Chesterfield's own pages

Land supply around Chesterfield

Amber Valley: 5.8 yearsAshfield: 3.86 yearsBassetlaw: 5.31 yearsBolsover: 4.82 yearsChesterfield: 3.46 yearsDerbyshire Dales: No current figure publishedDoncaster: 6.35 yearsGedling: 3.73 yearsMansfield: 5.53 yearsNewark and Sherwood: 4.02 yearsNorth East Derbyshire: 4.47 yearsRotherham: 4.4 yearsSheffield: No current figure publishedStaffordshire Moorlands: 2.95 years
6 years or more5 to 6 years4 to 5 years, or says it cannot show fiveUnder 4 yearsNo current figure published

Each council's own latest figure. The whole country: land supply map of England.

About this page

Planther keeps track of every council's plan, land supply position and appeal record, and rebuilds this page every night from what it holds. Figures are the council's own unless they are marked as an inspector's. If something here is wrong, email hello@planther.co.uk and we will put it right.

See Planther at work in Chesterfield

Ask Planther about a site and it does the research: the council's position, the appeals that matter, and a first draft, each point with its source. Here it answers a question about Chesterfield from the figures on this page.

Book a demo

We will show you round Planther, then set you up with a trial so you can try it on your own work. We can usually have you, or your whole firm, up and running the same day.

Bringing a whole firm? We can work to your own contract and data processing agreement, and invoice you directly.