The development plan is the North Northamptonshire Joint Core Strategy 2011-2031 (Part 1, July 2016), Wellingborough Local Plan Part 2 (February 2019), Corby Part 2 Local Plan (September 2021), Kettering Site Specific Part 2 Local Plan (December 2021), East Northamptonshire Local Plan Part 2 (December 2023), Kettering Town Centre Area Action Plan (July 2011), Northamptonshire Minerals and Waste Local Plan (Update, July 2017) and 26 made neighbourhood plans, plus the Isham Neighbourhood Plan since its referendum on 1 October 2026, adopted on 7 December 2023, covering 2011 to 2031. It replaced 2 earlier plans, including the Rural North, Oundle and Thrapston Plan (2011).
26 made neighbourhood plans; Isham passed referendum in October 2026, and Rothwell, Central Kettering, Little Addington and Wilbarston are near the end.
The North Northamptonshire Local Plan 2024-2045
Being prepared under the plan-making system introduced in 2026, which runs each plan through three gateways in about 30 months.
Now at gateway 1, step 3 of 9. Adoption expected in March 2029, 2 years and 4 months away.
- Notice of intention27 Apr 2026
- Scoping consultation20 May 2026
- NowGateway 114 Oct 2026
- Content and evidence consultationJan 2027
- Gateway 2July 2027
- Plan consultationOct 2027
- Gateway 3June 2028
- ExaminationJuly 2028
- AdoptionMar 2029
Notice of intention27 Apr 2026
Scoping consultation20 May 2026
Gateway 1Now14 Oct 2026
Content and evidence consultationJan 2027
Gateway 2July 2027
Plan consultationOct 2027
Gateway 3June 2028
ExaminationJuly 2028
AdoptionMar 2029
Dates from the council's published timetable, its local development scheme.
Source: the council's local plan pages. Checked 2026-11-12 (7 days ago). Every council: where each local plan has got to.