High Peak Council says it can show a 2.47-year supply of housing land, at 1 April 2025, measured against NPPF (December 2024) standard method, short of the five years national policy asks for.
The four most recent appeal decisions that dealt with land supply, from 8 May 2025 to 30 October 2026, all found the council could not show five years. Before that, inspectors found it could, most recently on 18 June 2024.
It scored 121% in the 2025 Housing Delivery Test, with no consequence listed.
Its local plan, the High Peak Local Plan (2016), was adopted on 1 April 2016.
Updated 2026-11-17 (2 days ago). Every figure links to where it comes from.