Cambridge: housing land supply, local plan and appeals

Cambridge Council says it can show a 2.75-year supply of housing land, at 1 April 2026, measured against local housing need (standard method), short of the five years national policy asks for.

The two most recent appeal decisions that dealt with land supply, from 11 August 2025 to 14 October 2026, both found the council could not show five years. Before that, inspectors found it could, most recently on 24 January 2024.

It scored 82% in the 2025 Housing Delivery Test, and the government's results list a 20% buffer as the consequence.

Its local plan, the Cambridge Local Plan 2018, was adopted on 18 October 2018. A replacement, the Greater Cambridge Local Plan 2024-2045, is at Regulation 19.

Updated 2026-11-17 (2 days ago). Every figure links to where it comes from.

Five-year housing land supply

Cambridge Council's latest published position is a 2.75-year supply of deliverable housing land for the period 2026 to 2031, made up of 3,583 homes it expects on deliverable sites. It is measured against local housing need (standard method).

Other councils in the East of England

Each council's own latest figure; base dates differ. All councils are on the land supply map of England.

Source: the council's land supply statement, published 2026-11. Checked 2026-11-16 (3 days ago).

What inspectors found at appeal

A council's own land supply figure is often tested at appeal. These are the most recent appeal decisions in Cambridge where the inspector dealt with land supply, and what each one found.

  1. Five years not shownNot disputed14 October 2026 - appeal dismissed
    Land At The Rear Of 31 Neale Close, Cambridge
    “The Council has confirmed that it cannot currently demonstrate a five-year supply of deliverable housing sites, with a housing land supply of 2.72 years.”
    Figures given: council 2.72 years. Decision 6008906
  2. Inspector did not decideDisputed27 August 2025 - appeal dismissed
    Land Rear Of, 226 To 250 Queen Ediths Way, Cambridge, Cambridgeshire
    “Even if, I accept the appellant's position that the Council can only demonstrate 3 years' supply”
    Figures given: appellant 3 years. Decision 3363192
  3. Five years not shownNot disputed11 August 2025 - appeal dismissed
    Go Glass, 127 Cherry Hinton Road, CAMBRIDGE
    “The delegated report accepts that the council can only identify 4.6 years of available housing land, leaving a shortfall of 0.4 years.”
    Figures given: council 4.6 years. Decision 3363985
  4. Five years shownNot disputed24 January 2024 - appeal dismissed
    303 Histon Road, CAMBRIDGE, Cambridgeshire
    “the delivery of additional dwellings would only be of moderate favourable weight as the Council can demonstrate a 5-year Housing Land Supply”
    Figures given: inspector 5 years. Decision 3317663
  5. Five years shownNot disputed8 November 2023 - appeal dismissed
    196-198 Green End Road, Cambridge, Cambridgeshire
    “the absence of any evidence indicating a shortfall in housing land supply”

Housing Delivery Test

The Housing Delivery Test compares the homes built in a council's area over three years with the number needed. Cambridge scored 82% in the 2025 measurement, published on 17 August 2026. The consequence listed in the government's results is: 20% buffer.

YearHomes neededHomes delivered
2022 to 2023685898
2023 to 2024705282
2024 to 2025687532

Source: Housing Delivery Test 2025 measurement. Every council's result: Housing Delivery Test results.

Local plan

The development plan is the Cambridge Local Plan 2018, Cambridge East Area Action Plan 2008 (except policies CE/3 and CE/35), North West Cambridge Area Action Plan 2009, Cambridgeshire and Peterborough Minerals and Waste Local Plan 2021 and South Newnham Neighbourhood Plan 2024-2041 (South Newnham area only), adopted on 18 October 2018, covering 2011 to 2031.

One made neighbourhood plan, South Newnham (2025); no other neighbourhood areas in the city.

The Greater Cambridge Local Plan 2024-2045

Being prepared under the plan-making system in place before 2026.

Now at regulation 19 consultation, step 3 of 7.

  1. Early preparation
  2. Regulation 18 consultationDec 2025
  3. NowRegulation 19 consultation3 Aug 2026
  4. SubmittedDec 2026
  5. Examination hearings2027-spring
  6. Main modifications
  7. Adoption
  1. Early preparation
  2. Regulation 18 consultationDec 2025
  3. Regulation 19 consultationNow3 Aug 2026
  4. SubmittedDec 2026
  5. Examination hearings2027-spring
  6. Main modifications
  7. Adoption

The Cambridgeshire and Peterborough Minerals and Waste Plan (review)

Being prepared under the plan-making system introduced in 2026, which runs each plan through three gateways in about 30 months.

Now at scoping consultation, step 2 of 9.

  1. Notice of intention3 Aug 2026
  2. NowScoping consultation3 Aug 2026
  3. Gateway 1
  4. Content and evidence consultation
  5. Gateway 2
  6. Plan consultation
  7. Gateway 3
  8. Examination
  9. Adoption
  1. Notice of intention3 Aug 2026
  2. Scoping consultationNow3 Aug 2026
  3. Gateway 1
  4. Content and evidence consultation
  5. Gateway 2
  6. Plan consultation
  7. Gateway 3
  8. Examination
  9. Adoption

Dates from the council's published timetable, its local development scheme.

Source: the council's local plan pages. Checked 2026-11-16 (3 days ago). Every council: where each local plan has got to.

Planning appeals

Since 2016, inspectors have decided 358 appeals against Cambridge's decisions and allowed 90 of them (25%), against 31% across all councils. For major schemes, 7 of 12 were allowed (58%, against 50% across all councils).

YearDecidedAllowedShare allowed
2019307 (23%)
2020232 (9%)
2021369 (25%)
20223913 (33%)
2023349 (26%)
20244410 (23%)
2025274 (15%)
2026277 (26%)

Decided means allowed, dismissed or split, with a decision date; a split decision counts as decided but not allowed. From the Planning Inspectorate's published decisions.

Cambridge's own pages

Land supply around Cambridge

Braintree: 5.32 yearsCambridge: 2.75 yearsCentral Bedfordshire: 3.93 yearsEast Cambridgeshire: 6.02 yearsHuntingdonshire: 4.28 yearsNorth Hertfordshire: 2.43 yearsSouth Cambridgeshire: 7.83 yearsUttlesford: 5.35 yearsWest Suffolk: 6.02 years
6 years or more5 to 6 years4 to 5 years, or says it cannot show fiveUnder 4 yearsNo current figure published

Each council's own latest figure. The whole country: land supply map of England.

About this page

Planther keeps track of every council's plan, land supply position and appeal record, and rebuilds this page every night from what it holds. Figures are the council's own unless they are marked as an inspector's. If something here is wrong, email hello@planther.co.uk and we will put it right.

See Planther at work in Cambridge

Ask Planther about a site and it does the research: the council's position, the appeals that matter, and a first draft, each point with its source. Here it answers a question about Cambridge from the figures on this page.

Book a demo

We will show you round Planther, then set you up with a trial so you can try it on your own work. We can usually have you, or your whole firm, up and running the same day.

Bringing a whole firm? We can work to your own contract and data processing agreement, and invoice you directly.