Watford: housing land supply, local plan and appeals

Watford Council says it can show a 5.44-year supply of housing land, at 1 April 2024, measured against 4,190 dwellings over 5 years (784 dwellings/year requirement, 5% buffer and equal apportionment of any shortfall).

It scored 95% in the 2025 Housing Delivery Test, with no consequence listed.

Its local plan, the Watford Local Plan: A Sustainable Town 2021-2038 (adopted 17 October 2022), was adopted on 17 October 2022. A replacement, the South West Herts Joint Strategic Plan, is at Regulation 18.

Updated 2026-11-17 (2 days ago). Every figure links to where it comes from.

Five-year housing land supply

Watford Council's latest published position is a 5.44-year supply of deliverable housing land for the period 2024 to 2029, made up of 4,557 homes it expects on deliverable sites. It is measured against 4,190 dwellings over 5 years (784 dwellings/year requirement, 5% buffer and equal apportionment of any shortfall).

This is the latest figure the council has published. Its base date is 1 April 2024, more than 18 months ago.

Other councils in the East of England

Each council's own latest figure; base dates differ. All councils are on the land supply map of England.

Source: the council's land supply statement, published 2025-05. Checked 2026-10-02 (7 weeks ago).

What inspectors found at appeal

A council's own land supply figure is often tested at appeal. These are the most recent appeal decisions in Watford where the inspector dealt with land supply, and what each one found.

  1. Five years not shownNot disputed21 October 2024 - appeal dismissed
    26 Woodford Road, WATFORD, Hertfordshire
    “the Council concedes it is unable to demonstrate a five-year supply of deliverable housing sites”
  2. Five years not shownNot disputed20 February 2024 - appeal dismissed
    8 Holtsmere Close, Watford
    “I am conscious that in this appeal the Council's failure to achieve its housing targets is an important consideration”

Housing Delivery Test

The Housing Delivery Test compares the homes built in a council's area over three years with the number needed. Watford scored 95% in the 2025 measurement, published on 17 August 2026. The consequence listed in the government's results is: None.

YearHomes neededHomes delivered
2022 to 2023781772
2023 to 2024784751
2024 to 2025784699

Source: Housing Delivery Test 2025 measurement. Every council's result: Housing Delivery Test results.

Local plan

The development plan is the Watford Local Plan: A Sustainable Town 2021-2038 (adopted 17 October 2022) and Hertfordshire minerals and waste plans (county), adopted on 17 October 2022, covering 2021 to 2038. It replaced 2 earlier plans, including the Watford Core Strategy (2006-2031).

No neighbourhood plans or neighbourhood plan areas in Watford.

The South West Herts Joint Strategic Plan

Being prepared under the plan-making system in place before 2026.

Now at regulation 18 consultation, step 2 of 7.

  1. Early preparation
  2. NowRegulation 18 consultationNov 2022
  3. Regulation 19 consultation
  4. Submitted
  5. Examination hearings
  6. Main modifications
  7. Adoption
  1. Early preparation
  2. Regulation 18 consultationNowNov 2022
  3. Regulation 19 consultation
  4. Submitted
  5. Examination hearings
  6. Main modifications
  7. Adoption

Dates from the council's published timetable, its local development scheme.

Source: the council's local plan pages. Checked 2026-09-30 (7 weeks ago). Every council: where each local plan has got to.

Planning appeals

Since 2016, inspectors have decided 448 appeals against Watford's decisions and allowed 153 of them (34%), against 31% across all councils. For major schemes, 4 of 8 were allowed (50%, against 50% across all councils).

YearDecidedAllowedShare allowed
20194318 (42%)
20206119 (31%)
20215619 (34%)
20224418 (41%)
20234714 (30%)
2024265 (19%)
20253614 (39%)
20262811 (39%)

Decided means allowed, dismissed or split, with a decision date; a split decision counts as decided but not allowed. From the Planning Inspectorate's published decisions.

Watford's own pages

Land supply around Watford

Barnet: No current figure publishedBrent: No current figure publishedBuckinghamshire: 0.86 yearsCamden: 2.8 yearsDacorum: 1.2 yearsEast Hertfordshire: 3.55 yearsEnfield: 3.1 yearsHaringey: No current figure publishedHarrow: 5.2 yearsHertsmere: No current figure publishedHillingdon: 2.5 yearsSt Albans: 1.12 yearsThree Rivers: 1.19 yearsWatford: 5.44 yearsWelwyn Hatfield: 1.8 yearsWindsor and Maidenhead: 3.53 years
6 years or more5 to 6 years4 to 5 years, or says it cannot show fiveUnder 4 yearsNo current figure published

Each council's own latest figure. The whole country: land supply map of England.

About this page

Planther keeps track of every council's plan, land supply position and appeal record, and rebuilds this page every night from what it holds. Figures are the council's own unless they are marked as an inspector's. If something here is wrong, email hello@planther.co.uk and we will put it right.

See Planther at work in Watford

Ask Planther about a site and it does the research: the council's position, the appeals that matter, and a first draft, each point with its source. Here it answers a question about Watford from the figures on this page.

Book a demo

We will show you round Planther, then set you up with a trial so you can try it on your own work. We can usually have you, or your whole firm, up and running the same day.

Bringing a whole firm? We can work to your own contract and data processing agreement, and invoice you directly.