West Suffolk: housing land supply, local plan and appeals

West Suffolk Council says it can show a 6.02-year supply of housing land, at 1 April 2026, measured against the Local Plan requirement of 765 homes a year (Policy SP14), plus a shortfall of 87 homes and a 20% buffer.

The four most recent appeal decisions that dealt with land supply, from 16 December 2025 to 14 May 2026, all found the council could show five years. Before that, inspectors found it could not, most recently on 16 September 2025.

It scored 89% in the 2025 Housing Delivery Test, and the government's results list an action plan as the consequence.

Its local plan, the West Suffolk Local Plan 2024-2041, was adopted on 15 July 2025. A replacement, the West Suffolk Local Plan 2045, is at the scoping consultation, with adoption expected in May 2029.

Updated 2026-11-17 (2 days ago). Every figure links to where it comes from.

Five-year housing land supply

West Suffolk Council's latest published position is a 6.02-year supply of deliverable housing land for the five years from 1 April 2026 (to 31 March 2031), made up of 5,658 homes it expects on deliverable sites. It is measured against the Local Plan requirement of 765 homes a year (Policy SP14), plus a shortfall of 87 homes and a 20% buffer.

The council applies a 20% buffer, and a Sedgefield approach to the earlier shortfall. Its previous assessment (December 2025) gave 6.0 years with a 5% buffer.

Other councils in the East of England

Each council's own latest figure; base dates differ. All councils are on the land supply map of England.

Source: the council's land supply statement, published August 2026. Checked 2026-10-05 (6 weeks ago).

What inspectors found at appeal

A council's own land supply figure is often tested at appeal. These are the most recent appeal decisions in West Suffolk where the inspector dealt with land supply, and what each one found.

  1. Five years shownDisputed14 May 2026 - appeal dismissed
    Land South Of, Grove Lane, Stanton, Suffolk
    “The appellant has not provided any substantive evidence to the contrary.”
    Figures given: council 6 years. Decision 6003142
  2. Five years shownNot disputed25 March 2026 - appeal dismissed
    Land At Pipers Hall Farm, Whepstead Road, Hawstead, Suffolk
    “The Council states that upon the recent adoption of the new Local Plan, it acquired a 5-year housing land supply. This has not been disputed by the appellant”
  3. Five years shownNot disputed19 March 2026 - appeal dismissed
    Land off Manor Lane, Horringer, Suffolk
    “there is no suggestion the Council cannot demonstrate a deliverable five year supply of housing land.”
  4. Five years shownNot disputed16 December 2025 - appeal dismissed
    Cornhill Walk Shoppping Centre, Bury St Edmunds
    “the Council is currently able to demonstrate a healthy housing land supply of around 6.13 years with a Housing Delivery Test measure of 129%.”
  5. Five years not shownDisputed16 September 2025 - appeal dismissed
    Dovecote Farm Hepworth Road, Hepworth Road, Thelnetham, Suffolk
    “The Council cannot for the purposes of this appeal demonstrate a deliverable five year supply of housing land as required by Paragraph 78 of the Framework.”
  6. Five years not shownDisputed10 September 2025 - appeal dismissed
    Land Adjacent to Montescourt, Philip Road, Bury St Edmunds, Suffolk
    “The Council cannot for the purposes of this appeal demonstrate a deliverable five year supply of housing land as required by Paragraph 78 of the Framework.”
  7. Five years not shownDisputed1 July 2025 - appeal dismissed
    Land to the rear of 35 to 44a, Queens Road, Bury St Edmunds, Suffolk
    “However, I have based my assessment on the Council's current land supply of 3.6 years, which is significantly short of Government expectations.”
    Figures given: council 3.6 years, inspector 3.6 years. Decision 3356609
  8. Five years not shownNot disputed24 June 2025 - appeal dismissed
    Land East of Rede Road, Whepstead, Suffolk
    “The Council is currently unable to demonstrate a 5 year supply of housing land and therefore Framework Paragraph 11.d)ii., would apply”

Showing the 8 most recent of 18 decisions in West Suffolk that dealt with land supply. Planther searches and reads all of them for a site.

Housing Delivery Test

The Housing Delivery Test compares the homes built in a council's area over three years with the number needed. West Suffolk scored 89% in the 2025 measurement, published on 17 August 2026. The consequence listed in the government's results is: Action plan.

YearHomes neededHomes delivered
2022 to 2023796971
2023 to 2024790483
2024 to 2025765642

Source: Housing Delivery Test 2025 measurement. Every council's result: Housing Delivery Test results.

Local plan

The development plan is the West Suffolk Local Plan 2024-2041, adopted on 15 July 2025, covering 2024 to 2041. It replaced 8 earlier plans, including the St Edmundsbury Core Strategy (2010).

Ten neighbourhood plans are made in West Suffolk; Barningham has passed its referendum and Barton Mills is being examined.

The West Suffolk Local Plan 2045

Being prepared under the plan-making system introduced in 2026, which runs each plan through three gateways in about 30 months.

Now at scoping consultation, step 2 of 9. Adoption expected in May 2029, 2 years and 6 months away.

Gateway 1 was due on 29 October 2026. The council has not yet published it as done; its own page will say whether it happened on time.

  1. Notice of intention16 June 2026
  2. NowScoping consultation16 June 2026
  3. Gateway 129 Oct 2026
  4. Content and evidence consultationMay 2027
  5. Gateway 2Sep 2027
  6. Plan consultationJune 2028
  7. Gateway 3Sep 2028
  8. ExaminationOct 2028
  9. AdoptionMay 2029
  1. Notice of intention16 June 2026
  2. Scoping consultationNow16 June 2026
  3. Gateway 129 Oct 2026
  4. Content and evidence consultationMay 2027
  5. Gateway 2Sep 2027
  6. Plan consultationJune 2028
  7. Gateway 3Sep 2028
  8. ExaminationOct 2028
  9. AdoptionMay 2029

Dates from the council's published timetable, its local development scheme.

Source: the council's local plan pages. Checked 2026-10-05 (6 weeks ago). Every council: where each local plan has got to.

Planning appeals

Since 2016, inspectors have decided 460 appeals against West Suffolk's decisions and allowed 123 of them (27%), against 31% across all councils. For major schemes, 8 of 15 were allowed (53%, against 50% across all councils).

YearDecidedAllowedShare allowed
2019539 (17%)
20203812 (32%)
2021469 (20%)
20224611 (24%)
20235314 (26%)
2024307 (23%)
20254515 (33%)
2026308 (27%)

Decided means allowed, dismissed or split, with a decision date; a split decision counts as decided but not allowed. From the Planning Inspectorate's published decisions.

West Suffolk's own pages

Land supply around West Suffolk

Babergh: 4.68 yearsBarnet: No current figure publishedBasildon: 2.05 yearsBedford: 3.35 yearsBoston: 4.8 yearsBraintree: 5.32 yearsBreckland: 2.88 yearsBrentwood: 4.53 yearsBroadland: 4.37 yearsBroxbourne: 2.13 yearsBuckinghamshire: 0.86 yearsCambridge: 2.75 yearsCentral Bedfordshire: 3.93 yearsChelmsford: 4.74 yearsColchester: 5.05 yearsDacorum: 1.2 yearsEast Cambridgeshire: 6.02 yearsEast Hertfordshire: 3.55 yearsEast Suffolk: 3.07 yearsEnfield: 3.1 yearsEpping Forest: No current figure publishedFenland: 6.6 yearsGreat Yarmouth: 6.06 yearsHarborough: 3.1 yearsHaringey: No current figure publishedHarlow: 4.9 yearsHarrow: 5.2 yearsHavering: 3 yearsHertsmere: No current figure publishedHillingdon: 2.5 yearsHuntingdonshire: 4.28 yearsIpswich: 3.46 yearsKing's Lynn and West Norfolk: 6.2 yearsLuton: 4.64 yearsMaldon: 2.8 yearsMelton: 7.6 yearsMid Suffolk: 6.73 yearsMilton Keynes: 5.47 yearsNorth Hertfordshire: 2.43 yearsNorth Kesteven: 7.1 yearsNorth Norfolk: 7.3 yearsNorth Northamptonshire: 4.35 yearsNorwich: 4.37 yearsPeterborough: 4.38 yearsRedbridge: Says it cannot show five yearsRochford: 2 yearsRushcliffe: 5.1 yearsRutland: 4.34 yearsSouth Cambridgeshire: 7.83 yearsSouth Holland: 4.6 yearsSouth Kesteven: 4.07 yearsSouth Norfolk: 4.37 yearsSt Albans: 1.12 yearsStevenage: 5.59 yearsTendring: 3.52 yearsThree Rivers: 1.19 yearsUttlesford: 5.35 yearsWaltham Forest: 5.05 yearsWatford: 5.44 yearsWelwyn Hatfield: 1.8 yearsWest Northamptonshire: No current figure publishedWest Suffolk: 6.02 years
6 years or more5 to 6 years4 to 5 years, or says it cannot show fiveUnder 4 yearsNo current figure published

Each council's own latest figure. The whole country: land supply map of England.

About this page

Planther keeps track of every council's plan, land supply position and appeal record, and rebuilds this page every night from what it holds. Figures are the council's own unless they are marked as an inspector's. If something here is wrong, email hello@planther.co.uk and we will put it right.

See Planther at work in West Suffolk

Ask Planther about a site and it does the research: the council's position, the appeals that matter, and a first draft, each point with its source. Here it answers a question about West Suffolk from the figures on this page.

Book a demo

We will show you round Planther, then set you up with a trial so you can try it on your own work. We can usually have you, or your whole firm, up and running the same day.

Bringing a whole firm? We can work to your own contract and data processing agreement, and invoice you directly.