North Hertfordshire: housing land supply, local plan and appeals

North Hertfordshire Council says it can show a 2.43-year supply of housing land, at 31 March 2026, measured against Adopted Local Plan 2011-2031 stepped housing requirement (plan under five years old), short of the five years national policy asks for.

The 12 most recent appeal decisions that dealt with land supply, from 11 December 2024 to 30 October 2026, all found the council could not show five years.

It scored 75% in the 2025 Housing Delivery Test, and the government's results list a 20% buffer as the consequence.

Its local plan, the North Hertfordshire Local Plan 2011-2031, was adopted on 8 November 2022. A replacement, the North Hertfordshire Local Plan (to 2040), is at the content and evidence consultation, with adoption expected on 5 January 2029.

Updated 2026-11-17 (2 days ago). Every figure links to where it comes from.

Five-year housing land supply

North Hertfordshire Council's latest published position is a 2.43-year supply of deliverable housing land for the period 2026/27 to 2030/31, made up of 4,389 homes it expects on deliverable sites. It is measured against Adopted Local Plan 2011-2031 stepped housing requirement (plan under five years old).

Other councils in the East of England

Each council's own latest figure; base dates differ. All councils are on the land supply map of England.

Source: the council's land supply statement, published 2026-09. Checked 2026-10-26 (3 weeks ago).

What inspectors found at appeal

A council's own land supply figure is often tested at appeal. These are the most recent appeal decisions in North Hertfordshire where the inspector dealt with land supply, and what each one found.

  1. Five years not shownNot disputed30 October 2026 - appeal dismissed
    Glencoe Villa, Snailswell Lane, Ickleford
    “The proposal is for a single dwelling in circumstances where there is 2.6 years supply of deliverable housing sites compared to the five years required by the Framework.”
    Figures given: council 2.6 years, inspector 2.6 years. Decision 6012789
  2. Five years not shownNot disputed19 October 2026 - appeal dismissed
    Land to the front of Everglades, Maiden Street, Weston, Hitchin
    “The Council is also unable to identify a supply of deliverable sites sufficient to provide a minimum of 5 years' worth of housing”
  3. Five years not shownNot disputed29 July 2026 - appeal dismissed
    L/A 1 Caldecote Road, Newnham, Baldock, Hertfordshire
    “The Council accepts that it cannot demonstrate a five year supply of deliverable housing sites and estimates this figure to be 3.3 years.”
    Figures given: council 3.3 years. Decision 6007832
  4. Five years not shownNot disputed7 July 2026 - appeal allowed
    Land off Barkway Road and North of Flint Hall, Barkway Road, Easting: 536403; Northing: 239870, Royston
    “The Council cannot demonstrate a 5 year housing supply, with the figure standing at 2.6 years. This equates to a shortfall of some 3,347 dwellings.”
  5. Five years not shownNot disputed24 October 2025 - appeal dismissed
    Trees, Gosmore Road, HITCHIN, Herts
    “The Council accepts that it cannot demonstrate a five-year supply of deliverable housing land”
  6. Five years not shownNot disputed15 September 2025 - appeal dismissed
    Old School House, Park Lane, Old Knebworth, Hertfordshire
    “The Council concedes that it cannot currently demonstrate a five-year supply of deliverable housing sites”
  7. Five years not shownNot disputed27 June 2025 - appeal allowed
    Land north of Ashwell Street, Ashwell
    “They confirmed that its supply stands at less than this at 3.9 years.”
    Figures given: council 3.9 years. Decision 3349177
  8. Five years not shownNot disputed23 June 2025 - appeal dismissed
    10 St. Katherines Close, Ickleford, HITCHIN, Hertfordshire
    “The Council is unable to demonstrate a five-year supply of housing land, as required by the Framework.”

Showing the 8 most recent of 16 decisions in North Hertfordshire that dealt with land supply. Planther searches and reads all of them for a site.

Housing Delivery Test

The Housing Delivery Test compares the homes built in a council's area over three years with the number needed. North Hertfordshire scored 75% in the 2025 measurement, published on 17 August 2026. The consequence listed in the government's results is: 20% buffer.

YearHomes neededHomes delivered
2022 to 2023500447
2023 to 2024500426
2024 to 2025910551

Source: Housing Delivery Test 2025 measurement. Every council's result: Housing Delivery Test results.

Local plan

The development plan is the North Hertfordshire Local Plan 2011-2031 and Made neighbourhood plans (10), adopted on 8 November 2022, covering 2011 to 2031. It replaced the North Hertfordshire District Local Plan No. 2 with Alterations (1996).

Ten made neighbourhood plans; Charlton, Kimpton, St Ippolyts and St Pauls Walden are designated areas with no plan yet.

The North Hertfordshire Local Plan (to 2040)

Being prepared under the plan-making system introduced in 2026, which runs each plan through three gateways in about 30 months.

Now at content and evidence consultation, step 4 of 9. Adoption expected on 5 January 2029, 2 years and 2 months away.

  1. Notice of intention24 Apr 2026
  2. Scoping consultation11 May 2026
  3. Gateway 19 Oct 2026
  4. NowContent and evidence consultation13 Oct 2026
  5. Gateway 25 Apr 2027
  6. Plan consultation26 Oct 2027
  7. Gateway 327 Mar 2028
  8. Examination31 May 2028
  9. Adoption5 Jan 2029
  1. Notice of intention24 Apr 2026
  2. Scoping consultation11 May 2026
  3. Gateway 19 Oct 2026
  4. Content and evidence consultationNow13 Oct 2026
  5. Gateway 25 Apr 2027
  6. Plan consultation26 Oct 2027
  7. Gateway 327 Mar 2028
  8. Examination31 May 2028
  9. Adoption5 Jan 2029

Dates from the council's published timetable, its local development scheme.

Source: the council's local plan pages. Checked 2026-10-26 (3 weeks ago). Every council: where each local plan has got to.

Planning appeals

Since 2016, inspectors have decided 293 appeals against North Hertfordshire's decisions and allowed 82 of them (28%), against 31% across all councils. For major schemes, 13 of 19 were allowed (68%, against 50% across all councils).

YearDecidedAllowedShare allowed
2019327 (22%)
2020215 (24%)
20213112 (39%)
2022247 (29%)
2023274 (15%)
2024255 (20%)
20253210 (31%)
2026166 (38%)

Decided means allowed, dismissed or split, with a decision date; a split decision counts as decided but not allowed. From the Planning Inspectorate's published decisions.

North Hertfordshire's own pages

Land supply around North Hertfordshire

Babergh: 4.68 yearsBarking and Dagenham: No current figure publishedBarnet: No current figure publishedBasildon: 2.05 yearsBedford: 3.35 yearsBexley: 6.02 yearsBraintree: 5.32 yearsBreckland: 2.88 yearsBrent: No current figure publishedBrentwood: 4.53 yearsBroxbourne: 2.13 yearsBuckinghamshire: 0.86 yearsCambridge: 2.75 yearsCamden: 2.8 yearsCastle Point: 0.91 yearsCentral Bedfordshire: 3.93 yearsChelmsford: 4.74 yearsCherwell: 3.1 yearsColchester: 5.05 yearsDacorum: 1.2 yearsEaling: 5 yearsEast Cambridgeshire: 6.02 yearsEast Hertfordshire: 3.55 yearsEnfield: 3.1 yearsEpping Forest: No current figure publishedFenland: 6.6 yearsGreenwich: 3.02 yearsHackney: No current figure publishedHammersmith and Fulham: No current figure publishedHarborough: 3.1 yearsHaringey: No current figure publishedHarlow: 4.9 yearsHarrow: 5.2 yearsHavering: 3 yearsHertsmere: No current figure publishedHillingdon: 2.5 yearsHounslow: No current figure publishedHuntingdonshire: 4.28 yearsIslington: No current figure publishedKensington and Chelsea: 5 yearsLambeth: 4.21 yearsLewisham: No current figure publishedCity of London: 7.7 yearsLuton: 4.64 yearsMaldon: 2.8 yearsMedway: 3.1 yearsMid Suffolk: 6.73 yearsMilton Keynes: 5.47 yearsNewham: No current figure publishedNorth Hertfordshire: 2.43 yearsNorth Northamptonshire: 4.35 yearsOxford: 2.88 yearsReading: 3.55 yearsRedbridge: Says it cannot show five yearsRichmond upon Thames: 4.5 yearsRochford: 2 yearsRugby: 3.4 yearsSlough: No current figure publishedSouth Cambridgeshire: 7.83 yearsSouth Oxfordshire: 4.46 yearsSouthend-on-Sea: No current figure publishedSouthwark: No current figure publishedSt Albans: 1.12 yearsStevenage: 5.59 yearsStratford-on-Avon: 2.43 yearsThree Rivers: 1.19 yearsThurrock: 1.02 yearsTower Hamlets: No current figure publishedUttlesford: 5.35 yearsVale of White Horse: 5.51 yearsWaltham Forest: 5.05 yearsWatford: 5.44 yearsWelwyn Hatfield: 1.8 yearsWest Berkshire: 5.7 yearsWest Northamptonshire: No current figure publishedWest Suffolk: 6.02 yearsWestminster: 5.19 yearsWindsor and Maidenhead: 3.53 yearsWokingham: 2.5 years
6 years or more5 to 6 years4 to 5 years, or says it cannot show fiveUnder 4 yearsNo current figure published

Each council's own latest figure. The whole country: land supply map of England.

About this page

Planther keeps track of every council's plan, land supply position and appeal record, and rebuilds this page every night from what it holds. Figures are the council's own unless they are marked as an inspector's. If something here is wrong, email hello@planther.co.uk and we will put it right.

See Planther at work in North Hertfordshire

Ask Planther about a site and it does the research: the council's position, the appeals that matter, and a first draft, each point with its source. Here it answers a question about North Hertfordshire from the figures on this page.

Book a demo

We will show you round Planther, then set you up with a trial so you can try it on your own work. We can usually have you, or your whole firm, up and running the same day.

Bringing a whole firm? We can work to your own contract and data processing agreement, and invoice you directly.