The development plan is the Central Bedfordshire Local Plan 2015-2035 (adopted 22 July 2021), Saved policies of the Mid Bedfordshire Site Allocations DPD 2011 (HA9, HA11-HA14, HA20, HA24, HA29, MA2-MA5, MA8, EA1-EA3, EA5, EA7), Saved policies of the Mid Bedfordshire Local Plan 2005 (H08(2), H08(8), H08(26A), EMP4(1),(2),(3),(6),(10a), EMP12, BE10), Saved policies of the South Bedfordshire Local Plan Review 2004 (H1(3),(4),(5),(8),(13),(19),(27),(31), R2-R9, BE10), Minerals and Waste Local Plan: Strategic Sites and Policies (adopted by Central Bedfordshire 30 January 2014, joint with Bedford and Luton), Saved policies of the Bedfordshire and Luton Minerals and Waste Local Plan 2005 for Central Bedfordshire (W4, W5, W16, W17, W22, GE1-GE27) and 22 made neighbourhood plans, each in its own parish, adopted on 22 July 2021, covering 2015 to 2035. It replaced 2 earlier plans, including the Mid Bedfordshire Core Strategy and Development Management Policies DPD 2009.
Twenty-two neighbourhood plans have been made in Central Bedfordshire and form part of the development plan for their areas. Leighton-Linslade's plan is at examination and Moggerhanger's is at Regulation 16 consultation until 4 November 2026.
The Central Bedfordshire Local Plan 2050
Being prepared under the plan-making system introduced in 2026, which runs each plan through three gateways in about 30 months.
Now at gateway 1, step 3 of 9. Adoption expected on 28 December 2028, 2 years and 1 month away.
- Notice of intention26 Mar 2026
- Scoping consultation6 May 2026
- NowGateway 123 Oct 2026
- Content and evidence consultation30 Nov 2026
- Gateway 231 Mar 2027
- Plan consultation27 Oct 2027
- Gateway 35 Apr 2028
- Examination1 June 2028
- Adoption28 Dec 2028
Notice of intention26 Mar 2026
Scoping consultation6 May 2026
Gateway 1Now23 Oct 2026
Content and evidence consultation30 Nov 2026
Gateway 231 Mar 2027
Plan consultation27 Oct 2027
Gateway 35 Apr 2028
Examination1 June 2028
Adoption28 Dec 2028
The Bedfordshire Minerals and Waste Plan
Being prepared under the plan-making system introduced in 2026, which runs each plan through three gateways in about 30 months.
Now at scoping consultation, step 2 of 9. Adoption expected on 28 September 2029, 2 years and 10 months away.
- Notice of intention5 Oct 2026
- NowScoping consultation12 Oct 2026
- Gateway 131 Mar 2027
- Content and evidence consultation
- Gateway 2
- Plan consultation
- Gateway 3
- Examination
- Adoption28 Sep 2029
Notice of intention5 Oct 2026
Scoping consultationNow12 Oct 2026
Gateway 131 Mar 2027
Content and evidence consultation
Gateway 2
Plan consultation
Gateway 3
Examination
Adoption28 Sep 2029
Dates from the council's published timetable, its local development scheme.
Source: the council's local plan pages. Checked 2026-10-29 (3 weeks ago). Every council: where each local plan has got to.