Elmbridge Council says it can show a 1-year supply of housing land, at 31 March 2025, measured against local housing need (standard method, December 2024 NPPF), because the Core Strategy requirement is out of date, short of the five years national policy asks for.
The 12 most recent appeal decisions that dealt with land supply, from 2 February 2026 to 5 November 2026, all found the council could not show five years.
It scored 59% in the 2025 Housing Delivery Test, and the government's results list the presumption in favour of sustainable development as the consequence.
Its local plan, the Elmbridge Core Strategy (adopted 20 July 2011), was adopted on 15 April 2015. A replacement, the Elmbridge Local Plan 2039, is after the notice of intention, with adoption expected on 16 August 2029.
Updated 2026-11-17 (2 days ago). Every figure links to where it comes from.