Hart Council says it can show a 2.07-year supply of housing land, at 1 April 2025, measured against Local Housing Need (standard method, December 2024 revision) from May 2025; previously measured against the Local Plan's 423 dwellings a year requirement, short of the five years national policy asks for.

The seven most recent appeal decisions that dealt with land supply, from 19 August 2025 to 2 April 2026, all found the council could not show five years. Before that, inspectors found it could, most recently on 30 August 2024.

It scored 137% in the 2025 Housing Delivery Test, with no consequence listed.

Its local plan, the Hart Local Plan (Strategy and Sites) 2032 (2020), was adopted on 30 April 2020. A replacement, the Hart Local Plan 2044, is at the content and evidence consultation, with adoption expected on 31 October 2028.

Updated 2026-11-17 (2 days ago). Every figure links to where it comes from.

Five-year housing land supply

Hart Council's latest published position is a 2.07-year supply of deliverable housing land. It is measured against Local Housing Need (standard method, December 2024 revision) from May 2025; previously measured against the Local Plan's 423 dwellings a year requirement.

This is the latest figure the council has published. Its base date is 1 April 2025, more than 18 months ago.

Other councils in the South East

Each council's own latest figure; base dates differ. All councils are on the land supply map of England.

Source: the council's land supply statement, published 2025-12. Checked 2026-11-15 (4 days ago).

What inspectors found at appeal

A council's own land supply figure is often tested at appeal. These are the most recent appeal decisions in Hart where the inspector dealt with land supply, and what each one found.

  1. Five years not shownNot disputed2 April 2026 - appeal dismissed
    Land rear of Horns Farm House, Lower Common, Eversley Hook
    “The Council acknowledge that they are unable to demonstrate a five-year land supply of deliverable housing (5YHLS).”
    Figures given: council 2.07 years. Decision 6003255
  2. Five years not shownNot disputed1 April 2026 - appeal dismissed
    Brocketts Farm, Hulfords Lane, Hartley Wintney, Hampshire
    “The proposal would result in a small contribution of one dwelling, in the context of a lack of five-year housing land supply.”
  3. Five years not shownNot disputed4 November 2025 - appeal dismissed
    Amethyst Fields, Crookham Village, Fleet, Hampshire
    “As the Council acknowledge it is incapable of demonstrating an adequate five year supply of housing land with appropriate buffer, the provisions of Framework paragraph 11 d) are engaged.”
  4. Five years not shownNot disputed4 November 2025 - appeal allowed
    The Tileries Heath Lane, Ewshot, FARNHAM
    “as the Council are incapable of demonstrating an adequate five year supply of housing land with appropriate buffer, the provisions of Framework paragraph 11 d) are engaged.”
  5. Five years not shownNot disputed3 November 2025 - appeal allowed
    38 Rounton Road, Church Crookham, Fleet, Hampshire
    “the Council is unable to demonstrate a five-year housing supply. There is, therefore, a presumption in favour of sustainable development”
  6. Five years not shownNot disputed17 October 2025 - appeal dismissed
    12 Reading Road South, FLEET, Hampshire
    “as the Council acknowledge it is incapable of demonstrating an adequate five year supply of housing land with appropriate buffer, the provisions of Framework paragraph 11 d) are engaged”
  7. Inspector did not decideDisputed16 September 2025 - appeal dismissed
    Harewarren Farm, Chalky Lane, Dogmersfield, Hook, Hampshire
    “I have not been provided with any evidence from the Council to refute this”
    Figures given: appellant 2.72 years. Decision 3359381
  8. Five years not shownNot disputed19 August 2025 - appeal allowed
    General, Geffreys House, London Road, Hook, Hampshire
    “The Council can only demonstrate 1.8 years housing land supply and therefore, under paragraph 11d) of the Framework, the tilted balance applies.”
    Figures given: council 1.8 years, inspector 1.8 years. Decision 3363555

Showing the 8 most recent of 12 decisions in Hart that dealt with land supply. Planther searches and reads all of them for a site.

Housing Delivery Test

The Housing Delivery Test compares the homes built in a council's area over three years with the number needed. Hart scored 137% in the 2025 measurement, published on 17 August 2026. The consequence listed in the government's results is: None.

YearHomes neededHomes delivered
2022 to 2023295581
2023 to 2024299434
2024 to 2025297202

Source: Housing Delivery Test 2025 measurement. Every council's result: Housing Delivery Test results.

Local plan

The development plan is the Hart Local Plan (Strategy and Sites) 2032 (2020) and Saved policies of the Hart Local Plan (Replacement) 1996-2006, adopted on 30 April 2020, covering 2014 to 2032.

Ten made neighbourhood plans cover parishes across Hart District, with an eleventh (Eversley) currently seeking designation.

The Hart Local Plan 2044

Being prepared under the plan-making system introduced in 2026, which runs each plan through three gateways in about 30 months.

Now at content and evidence consultation, step 4 of 9. Adoption expected on 31 October 2028, 1 year and 11 months away.

  1. Notice of intention29 Apr 2026
  2. Scoping consultation27 May 2026
  3. Gateway 123 Sep 2026
  4. NowContent and evidence consultation26 Oct 2026
  5. Gateway 230 June 2027
  6. Plan consultation3 Sep 2027
  7. Gateway 33 Jan 2028
  8. Examination31 Mar 2028
  9. Adoption31 Oct 2028
  1. Notice of intention29 Apr 2026
  2. Scoping consultation27 May 2026
  3. Gateway 123 Sep 2026
  4. Content and evidence consultationNow26 Oct 2026
  5. Gateway 230 June 2027
  6. Plan consultation3 Sep 2027
  7. Gateway 33 Jan 2028
  8. Examination31 Mar 2028
  9. Adoption31 Oct 2028

Dates from the council's published timetable, its local development scheme.

Source: the council's local plan pages. Checked 2026-11-15 (4 days ago). Every council: where each local plan has got to.

Planning appeals

Since 2016, inspectors have decided 511 appeals against Hart's decisions and allowed 178 of them (35%), against 31% across all councils. For major schemes, 12 of 26 were allowed (46%, against 50% across all councils).

YearDecidedAllowedShare allowed
20196921 (30%)
20204814 (29%)
20214617 (37%)
20224619 (41%)
20236623 (35%)
20245220 (38%)
20255420 (37%)
20263011 (37%)

Decided means allowed, dismissed or split, with a decision date; a split decision counts as decided but not allowed. From the Planning Inspectorate's published decisions.

Hart's own pages

Land supply around Hart

Barnet: No current figure publishedBasingstoke and Deane: 3.2 yearsBracknell Forest: 3.53 yearsBrent: No current figure publishedBuckinghamshire: 0.86 yearsChichester: 5.16 yearsCrawley: 5.4 yearsEaling: 5 yearsEast Hampshire: 2.9 yearsEastleigh: 4.2 yearsElmbridge: 1 yearsEpsom and Ewell: Says it cannot show five yearsGuildford: 2.98 yearsHammersmith and Fulham: No current figure publishedHarrow: 5.2 yearsHart: 2.07 yearsHillingdon: 2.5 yearsHorsham: 1.7 yearsHounslow: No current figure publishedKensington and Chelsea: 5 yearsKingston upon Thames: 1.48 yearsMerton: 5.2 yearsMid Sussex: Says it cannot show five yearsMole Valley: 5.3 yearsNew Forest: 1.53 yearsReading: 3.55 yearsReigate and Banstead: 4.08 yearsRichmond upon Thames: 4.5 yearsRunnymede: 2.89 yearsRushmoor: 4.74 yearsSlough: No current figure publishedSouth Oxfordshire: 4.46 yearsSpelthorne: 5.3 yearsSurrey Heath: 7.71 yearsSutton: No current figure publishedTest Valley: 2.54 yearsVale of White Horse: 5.51 yearsWandsworth: 5.24 yearsWaverley: 1.28 yearsWest Berkshire: 5.7 yearsWiltshire: No current figure publishedWinchester: No current figure publishedWindsor and Maidenhead: 3.53 yearsWoking: 4.57 yearsWokingham: 2.5 years
6 years or more5 to 6 years4 to 5 years, or says it cannot show fiveUnder 4 yearsNo current figure published

Each council's own latest figure. The whole country: land supply map of England.

About this page

Planther keeps track of every council's plan, land supply position and appeal record, and rebuilds this page every night from what it holds. Figures are the council's own unless they are marked as an inspector's. If something here is wrong, email hello@planther.co.uk and we will put it right.

See Planther at work in Hart

Ask Planther about a site and it does the research: the council's position, the appeals that matter, and a first draft, each point with its source. Here it answers a question about Hart from the figures on this page.

Book a demo

We will show you round Planther, then set you up with a trial so you can try it on your own work. We can usually have you, or your whole firm, up and running the same day.

Bringing a whole firm? We can work to your own contract and data processing agreement, and invoice you directly.