Maidstone Council says it can show a 4.5-year supply of housing land, at 1 April 2025, measured against Local Plan Review requirement (1,000 homes a year, rising to 1,150 from 2028/29), plus 5% buffer, less 178 homes over-delivered since 2021, short of the five years national policy asks for.
The nine most recent appeal decisions that dealt with land supply, from 28 July 2025 to 5 October 2026, all found the council could not show five years. Before that, inspectors found it could, most recently on 7 July 2025.
It scored 93% in the 2025 Housing Delivery Test, and the government's results list an action plan as the consequence.
Its local plan, the Maidstone Borough Local Plan Review 2021-2038, was adopted on 20 March 2024.
Updated 2026-11-17 (2 days ago). Every figure links to where it comes from.